Google granted building permit for data center in Horndal

Google has now received a building permit from Avesta municipality for a data center on its land in Horndal, valid for two years. Groundwork began in November 2025, but the company has not yet made a formal decision to build. Preparatory work will continue until August.

Google purchased 109 hectares of forest land from Avesta municipality in 2017, an area equivalent to 150 football fields. For several years, the company stated that no business decision had been made regarding its use. However, in mid-November 2025, groundwork began in earnest, including blasting and heavy traffic, with up to 90 people involved at peak.

Avesta municipality has granted a building permit for a data center, valid for two years. Joakim Larsson, communications chief for Google Sweden, states: “We continue with various preparatory works on the land and are working to ensure we have all permits in place if we make a business decision to build a data center.” The plan is to complete the groundwork by August.

Local residents in Horndal have appealed parts of the plans, particularly the raising of the land by up to 10 meters where the server halls are to be located. Earlier in the process, municipal councilor Blerta Krenzi (S) welcomed Google's application for land permit as an “incredibly important step” for the area.

Related Articles

Aerial view of TeraWulf's Kentucky AI data center site showcasing modern facilities in a rural setting.
Image generated by AI

TeraWulf acquires Kentucky site for 1 GW AI data center

Reported by AI Image generated by AI

TeraWulf announced the purchase of a Kentucky development site to support more than 1 gigawatt of AI and high-performance computing capacity. The bitcoin miner turned infrastructure developer saw its stock rise 13 percent following the news.

Google has broken ground on its first Swedish datacenter in Horndal outside Avesta. The company promises thousands of jobs during construction and 100 permanent positions when the facility is ready in 2028.

Reported by AI

Google will build a data center in Horndal outside Avesta. The decision came after a long ten-year wait marked by expectations and criticism.

On April 21, Falun municipality decided to lease the land at Dikarbacken to a private actor. The move ends 13 years of provisional arrangements for the area near Falu Naturskola.

Reported by AI

Stockholm is set to replace the aging Hovet with a modern hockey arena for Djurgården and AIK. The project, known as Nya Hovet, involves two possible locations and is expected to begin construction between 2029 and 2030.

The Maine House and Senate approved LD 307 this week, imposing a moratorium on new data centers requiring 20 megawatts or more until at least October 2027. The bill, which prohibits state and local approvals for such facilities, now awaits action from Gov. Janet Mills amid national concerns over surging energy demands from AI infrastructure.

Reported by AI

The three waste piles in Dannemora, worrying residents for six years since Think Pink began dumping there in 2020, are set for removal. Östhammars municipality has placed responsibility on landowner Dannemora Iron AB, giving them two years. "We know people have been worried," says Lina Lendahl, team leader at the environmental unit.

 

 

 

This website uses cookies

We use cookies for analytics to improve our site. Read our privacy policy for more information.
Decline