Joburg Phase Three water shutdown starts: detailed impacts and prior phase updates

As Phase Three of Johannesburg Water's multi-phase maintenance program begins on 6 January 2026, residents in Soweto, Roodepoort and surrounds face low pressure and outages from a 54-hour Eikenhof shutdown. Reservoirs were pre-filled, tankers deployed; this follows Phase One disruptions and Phase Two postponement.

Johannesburg Water launched Phase Three of its critical maintenance on 6 January 2026 at 04:00, shutting down the Eikenhof pumping station until 8 January at 08:00. Full system recovery may take up to seven days, with low pressure or outages in elevated areas.

A 5 January media briefing at Turbine Hall detailed impacts on specific reservoirs: Roodepoort Deep (Hamberg, Rand Leases, Roodepoort, Creswell Park); Meadowlands 1 & 2 (Meadowlands zones, Tshepo Themba, Dube, Central Western Jabavu Ext 1, Mofolo Central/North, Orlando West, Zondi, Mmesi Park); Fleurhof; Doornkop (Eldorado Park, Nancefield, Pimville, Devland); Braamfischer (Braamfischer, Meadowlands, Mmesi Park).

Mayor Dada Morero confirmed reservoirs filled to 70% capacity beforehand. Roaming and stationary tankers will support affected zones. “We acknowledge the inconvenience... this work is essential to safeguarding the city’s long-term water security,” he said, emphasising collaboration with Rand Water.

Context from prior phases: Announced in December 2025, Phase One (Zuikerbosch, 13-15 Dec) caused extended outages beyond schedule, e.g., Midrand. Phase Two (Eikenhof, 19-21 Dec) was postponed due to technical issues and rescheduled before June 2026.

Separate incident: Joburg Water resolved a sewage leak on 30 December 2025 in Johannesburg CBD and Bezuidenhout Valley from a blocked manhole. Chlorine flushing and repairs followed; 5 January tests showed no E. coli but elevated coliforms. Supplies restricted during final checks, with normal service imminent.

関連記事

Collapsed transmission towers in Nelson Mandela Bay, South Africa, sparking amid power outages, with repair crews and affected residents in the dark.
AIによって生成された画像

Transmission towers collapse in Nelson Mandela Bay causing outages

AIによるレポート AIによって生成された画像

Two transmission towers collapsed in Nelson Mandela Bay on Thursday, leading to widespread power outages and water disruptions affecting businesses and residents. The municipality is spending R10 million on repairs, with a revised 10-day restoration timeline. Community efforts have supported vulnerable individuals during the crisis.

Residents of Johannesburg are preparing for potential water shortages over the festive season as Rand Water shuts down two key treatment stations for maintenance. The work, spanning from 13 December 2025 to 8 January 2026, will affect supplies in several areas including Soweto and Randburg. Authorities have outlined contingency measures, including deploying water tankers, to mitigate the impact.

AIによるレポート

The second phase of essential water infrastructure maintenance in Johannesburg begins on December 19, raising concerns for residents still recovering from extended outages in the first phase. This work targets the Eikenhof system and could affect supplies in several southern areas until December 21. Experts warn that full recovery may take days, potentially impacting holiday plans.

Residents in Olievenhoutbosch and nearby Pretoria areas spent Christmas without electricity due to a fire at a local substation caused by cable theft and vandalism. The outage has lasted three days, affecting daily life and businesses. Repair work is underway by City of Tshwane technicians.

AIによるレポート

The State Commission of Public Services of Tijuana (CESPT) reported that water supply restoration has reached 80% in the city and Playas de Rosarito. The outage stemmed from rehabilitation works on the Florido-Aguaje aqueduct and started recovering from Sunday afternoon. Officials urge rational water use during the gradual process.

Nairobi depends on a complex network of rivers, dams, and pipes to supply water to more than four million residents, yet shortages remain a daily reality in many neighborhoods. Rapid population growth and aging infrastructure contribute to these persistent issues. President William Ruto has revealed plans to increase water supply through the Northern Collector Tunnel.

AIによるレポート

The Passenger Rail Agency of South Africa (Prasa) has initiated restoration work on the Vereeniging train line south of Johannesburg, dormant for over five years since the Covid-19 lockdown. Vandalism led to the suspension, and recent efforts address a sinkhole and other infrastructure damage to resume services for local commuters.

 

 

 

このウェブサイトはCookieを使用します

サイトを改善するための分析にCookieを使用します。詳細については、プライバシーポリシーをお読みください。
拒否