Emcali and CVC present roadmap for second phase of PTAR Cañaveralejo

Emcali received the studies and detailed engineering designs for the secondary treatment of PTAR Cañaveralejo, a project aimed at reducing pollution in the Cauca River.

Emcali received the documents from CVC on July 16. They establish that the plant would increase organic matter removal from 30 % to 90 %, avoiding the discharge of 25 thousand tons of pollutants per year.

The initiative requires an estimated investment of 1.29 billion pesos and a four-year construction period. Emcali general manager Roger Mina stated that the delivery of the designs leaves the technical base ready to advance the project contracting.

CVC general director Marco Antonio Suárez highlighted that the studies eliminate technical uncertainty and constitute a roadmap for seeking financing. The consultancy was developed over 20 months with an investment exceeding 14 billion pesos.

Relaterte artikler

Agro-industrial leaders endorse new waterway contract after transparent tender
Bilde generert av AI

Agro-industrial entities endorse new waterway contract

Rapportert av AI Bilde generert av AI

After the final stage of the official tender was completed, agricultural and industrial entities praised the transparency of the process for the new waterway contract.

The Second Environmental Tribunal clarified on Thursday its May 14 ruling that partially annulled the environmental qualification resolution for the project of Compañía Minera Doña Inés de Collahuasi.

Rapportert av AI

Emcali presented a project to modernize 100% of Cali's public lighting with LED luminaires. The initiative involves over 186,000 luminaires and an investment of 450 billion pesos.

A citizen initiative in Montebello, Santiago de Cali, is transforming an emblematic public space with murals that reflect local biodiversity and culture.

Rapportert av AI

Colombian mining company Mineros S.A. announced it has obtained environmental certification for the processing plant and tailings deposit of the Porvenir project in Nicaragua. This milestone enables progress toward detailed engineering and future construction. The project holds reserves of 736,000 equivalent gold ounces.

The Kerala Water Authority has started a survey for a 27-km sewage pipeline in Kochi as part of a larger sewerage project under AMRUT 2.0.

Rapportert av AI

The Ministry of Mines and Energy announced an electrical interconnection with Venezuela through Vichada. The announcement came during the socialization of the El Merey Solar Plant, which will have 5 megawatts of capacity.

Dette nettstedet bruker informasjonskapsler

Vi bruker informasjonskapsler for analyse for å forbedre nettstedet vårt. Les vår personvernerklæring for mer informasjon.
Avvis