New Brixton reservoir opens year late as Johannesburg tackles water leaks

Johannesburg officials opened the new Brixton reservoir and tower this week, a year behind schedule. The project improves water pressure in the Commando system but leaves 43 other reservoirs still leaking across the city.

The Brixton reservoir and tower was due for completion by March 2025 but faced delays from late contractor payments. Since opening it has delivered better flow and pressure for six weeks in parts of the Commando system.

City data shows Johannesburg has 129 reservoirs and towers, of which 43 leak through walls or pipes. Johannesburg Water estimates it would cost R1.25 billion to fix them all and plans to repair 15 this year for R652 million.

Mayor Dada Morero said at the opening, “One project does not solve everything. But it is part of a bigger programme to restore reliability, rebuild confidence and improve the quality of services across the city.”

Non-revenue water stood at 48.7 percent in December 2025, with 26.3 percent lost through leaks and bursts. Johannesburg Water manages assets valued at R127 billion but notes investment levels remain below those of 15 years ago.

Relaterte artikler

Amid Johannesburg's ongoing water crisis—including a February confrontation at the site—the City launched the Brixton Reservoir and Water Tower on 29 April 2026, boosting storage capacity. Officials praised it as progress toward reliable supply, while critics highlighted persistent leaks, delays, and unproven resilience during outages.

Rapportert av AI

Residents in Johannesburg continue to face water shortages weeks after the commissioning of the Brixton Reservoir and Water Tower. A senior parliamentarian has highlighted governance and budget issues behind the recurring disruptions.

South Africa’s water sector lost nearly R19 billion in 2023/24 due to leaks, illegal connections and billing issues, Auditor-General Tsakani Maluleke’s report reveals. With 47% of treated water wasted before reaching users amid ageing infrastructure and governance failures, the findings underscore the urgency behind the National Water Crisis Committee launched in February.

Rapportert av AI

Ten years after a court ordered the City of Johannesburg to upgrade services in Slovo Park, residents still lack reliable water and sanitation. Partial electrification occurred in 2018, but basic needs remain unmet despite recent promises. Community members express ongoing frustration and hope amid slow delivery.