Japan halts Chubu Electric's Hamaoka nuclear restart screening

Japan's nuclear regulator has halted the screening process required to restart Chubu Electric Power's Hamaoka Nuclear Power Station due to inappropriate handling of seismic data. The utility admitted to using a method different from what it explained to regulators for selecting seismic waves. The move stalls efforts to resume operations at the plant, which has been idled since the 2011 Fukushima disaster.

On January 7, 2026, Japan's Nuclear Regulation Authority (NRA) announced it was halting the screening needed to restart Chubu Electric Power's Hamaoka Nuclear Power Station, following the utility's report of inappropriate seismic data handling for the regulatory review. Located on Japan's Pacific coast in Shizuoka Prefecture, the plant's two reactors have been idled since the 2011 Fukushima disaster, even as nuclear plants elsewhere in the country have resumed operations.

NRA Chairman Shinsuke Yamanaka told a regular commissioners' meeting, "This is fabrication of critical inspection data, which I clearly consider misconduct." He added, "There appears no objection to halting the review" for the Hamaoka plant's restart.

Chubu Electric disclosed on Tuesday that it had used a different method than explained to regulators to select seismic waves for the review. The revelation caused the company's shares to tumble nearly 10%, the steepest drop in more than 13 years. This incident underscores the stringent oversight in Japan's nuclear restart processes and raises questions about corporate governance in the utilities sector.

Makala yanayohusiana

Niigata Governor Hideyo Hanazumi announces restart of Kashiwazaki-Kariwa nuclear plant at press conference, with facility image projected behind.
Picha iliyoundwa na AI

Niigata approves restart of world's largest nuclear plant

Imeripotiwa na AI Picha iliyoundwa na AI

Niigata Governor Hideyo Hanazumi approved the restart of the world's largest nuclear plant, the Kashiwazaki-Kariwa facility, on Friday. This marks the first restart for operator TEPCO since the 2011 Fukushima disaster. The move supports Japan's goals to reduce fossil fuel reliance and achieve carbon neutrality.

Japan's Nuclear Regulation Authority has launched an on-site inspection at Chubu Electric Power's headquarters in Nagoya concerning fraudulent earthquake risk data linked to the Hamaoka nuclear power plant. The probe seeks to fully uncover the circumstances and motives behind the misconduct, which may have underestimated seismic ground motions at the facility. Depending on the findings, the authority could impose severe actions, such as disapproving reactor restarts or revoking the plant's installation permit.

Imeripotiwa na AI

Tokyo Electric Power Company restarted reactor No. 6 at the Kashiwazaki-Kariwa nuclear plant after about 14 years, but suspended operations just six hours after achieving a critical state due to an alarm. This event, the company's first restart since the 2011 Fukushima disaster, highlights ongoing safety concerns in Japan's nuclear revival.

South Korea has restarted the Gori-2 nuclear reactor at the Gori Nuclear Power Plant in Busan after a three-year suspension for safety checks and improvements. Operator Korea Hydro & Nuclear Power Co. received permission to resume operations last November. The reactor began commercial operations in April 1983 as the country's third nuclear power unit.

Imeripotiwa na AI

A Jiji Press opinion poll reveals that 44.7% of Japanese respondents support restarting idled nuclear power plants, while 26.1% oppose it. The findings closely mirror a survey from July 2022. Support levels vary significantly by political affiliation.

Japan's government plans to temporarily lift restrictions on coal-fired power plants to address an energy crunch from the Middle East war. Officials presented the plan to a panel of experts, who approved it, the industry ministry said. The measure allows full operation of older, less efficient coal plants for a year starting in the new fiscal year from April.

Imeripotiwa na AI

A U.S. nuclear decommissioning firm, Amentum Services Inc., plans to establish a training center in Futaba, Fukushima Prefecture, by 2029 to prepare workers for fuel debris removal at the Fukushima No. 1 nuclear power plant. The initiative anticipates full-scale operations as early as 2037 and seeks to build a steady supply of skilled personnel in collaboration with Tokyo Electric Power Company Holdings Inc. (TEPCO).

Jumapili, 22. Mwezi wa tatu 2026, 06:13:17

Kashiwazaki-Kariwa nuclear reactor resumes power generation

Ijumaa, 13. Mwezi wa tatu 2026, 03:16:43

Sanyo Shinkansen services suspended between Hakata and Hiroshima due to wire obstruction

Jumatatu, 2. Mwezi wa tatu 2026, 01:46:10

Japan aims to expand reuse of Fukushima decontamination soil

Jumatano, 25. Mwezi wa pili 2026, 00:03:25

Kashiwazaki-Kariwa No. 6 reactor restarts after scheduled halt

Jumatatu, 16. Mwezi wa pili 2026, 20:55:39

Tepco restarts power transmission from Kashiwazaki-Kariwa plant after 14 years

Jumatatu, 26. Mwezi wa kwanza 2026, 11:00:43

Japan approves Tepco's ¥3.1 trillion cost cuts in 10-year plan

Jumatano, 21. Mwezi wa kwanza 2026, 15:28:41

TEPCO restarts Kashiwazaki-Kariwa No. 6 reactor after delay

Alhamisi, 15. Mwezi wa kwanza 2026, 08:28:07

Chubu Electric president apologizes to mayor over Hamaoka nuclear data fraud

Jumanne, 16. Mwezi wa kumi na mbili 2025, 12:03:20

Launch of eighth H3 rocket halted at Tanegashima

Jumatatu, 15. Mwezi wa kumi na mbili 2025, 05:46:20

Japan to reconsider route of planned Hokuriku Shinkansen section

 

 

 

Tovuti hii inatumia vidakuzi

Tunatumia vidakuzi kwa uchambuzi ili kuboresha tovuti yetu. Soma sera ya faragha yetu kwa maelezo zaidi.
Kataa