Bogotá Metro hits 70% progress and 10 km viaduct milestone in early 2026

The Bogotá Metro project has advanced to over 70% completion as of early 2026, including a key milestone of 10 kilometers of viaduct constructed. Mayor Carlos Fernando Galán highlighted this progress, alongside the ongoing dynamic tests in the Bosa workshop, as the project enters its final stretch.

Construction of the Bogotá Metro, a major mobility project for Colombia's capital, has accelerated significantly. The contract, awarded in 2019 and received by the current administration at 28% progress in January 2024, now exceeds 70% as of early 2026. Mayor Carlos Fernando Galán announced this on his X account, stating the project is entering its 'home stretch.'

On January 3, 2026, workers completed the 10-kilometer viaduct mark, including the placement of the S503 span, totaling over 10,025 meters. 'Another milestone for the Bogotá Metro. On January 3 we reached ten kilometers of viaduct built... We continue advancing,' Galán noted.

This follows recent developments, including the start of dynamic tests for the first trains in the Bosa workshop yard after track electrification. These tests are a crucial step toward operational readiness, with projections for 90% overall progress by the end of 2026.

In December 2025, the administration secured US$1.060 million in credits from the World Bank and Inter-American Development Bank to fund ongoing works.

ተያያዥ ጽሁፎች

President Sheinbaum cuts ribbon at inauguration of Mexico-Toluca 'El Insurgente' train after 12 years, crowd celebrates new 58km commuter line.
በ AI የተሰራ ምስል

Mexico-Toluca train completes operations after 12 years of construction

በAI የተዘገበ በ AI የተሰራ ምስል

President Claudia Sheinbaum inaugurated on February 2, 2026, the final stage of the Mexico-Toluca Interurban Train, known as 'El Insurgente', a project started in 2014 with a 100 billion peso investment. This 57.7-kilometer line connects Toluca to western Mexico City, serving over 230,000 daily passengers. The project features seven stations and links to the Metro and Cablebús systems.

The fourth train for Bogotá's Metro Line 1 has arrived at the Bosa workshop from Quingdao, China, following the start of dynamic tests on the first three trains. Mayor Carlos Fernando Galán announced the milestone, noting steady progress toward 90% completion by end-2026 and ongoing deliveries every 15 days until October.

በAI የተዘገበ

Mayor Carlos Fernando Galán announced that the first three Bogotá metro trains are now conducting dynamic tests in the Bosa workshop yard. This milestone follows the electrification of the rail tracks, gearing up the system for up to 30 trains on the first line. Each train will complete 2,500 kilometers of tests in the city, mirroring those done in China.

The Agencia Nacional de Infraestructura (ANI) confirmed that the Devimed project, Desarrollo Vial del Oriente Medellín, will begin its reversion stage between July 29 and 31, 2026. This process will end with the formal handover of the infrastructure to Invías. For the preceding five months, the concessionaire will remain responsible for operations and maintenance.

በAI የተዘገበ

Montería's city hall launches Businú, Colombia's first mass public river transport system, turning the Sinú River into a key urban mobility axis. The project starts with two vessels and aims to cut travel times in the city. Mayor Hugo Kerguelén emphasized the historic shift in utilizing the river.

President Gustavo Petro announced the end of private road concessions as his government's primary budget-saving measure, shifting management to the state to potentially reduce tolls. This follows the recent confirmation of a 5.30% toll increase starting January 2026 tied to inflation.

በAI የተዘገበ

Colombia's National Infrastructure Agency and Ministry of Transport announced that toll fees will rise by 5.10% starting January 16, 2026, based on last year's IPC variation as reported by Dane. Additionally, 15 tolls will see an extra increase due to the normalization process under Decree 050.

 

 

 

ይህ ድረ-ገጽ ኩኪዎችን ይጠቀማል

የእኛን ጣቢያ ለማሻሻል ለትንታኔ ኩኪዎችን እንጠቀማለን። የእኛን የሚስጥር ፖሊሲ አንብቡ የሚስጥር ፖሊሲ ለተጨማሪ መረጃ።
ውድቅ አድርግ