Rain exposes leakage issues in Chennai Metro Rail phase II stations

Immagine generata dall'IA

A sudden downpour on Monday morning exposed heavy leakages in some stations of Chennai Metro Rail's upcoming phase II project along the Poonamallee-Porur stretch. The issue has led to further postponement of the section's launch. Officials have initiated urgent repairs.

A sudden downpour on Monday morning exposed heavy leakages in some stations along the Poonamallee-Porur elevated section of corridor 4 in Chennai Metro Rail's 118.9 km phase II project, which was slated for imminent launch.

The Commissioner of Metro Railway Safety granted final clearance for the Poonamallee-Porur stretch in the last week of February, subject to curbs on speed and frequency. However, the safety certificate restricted train services on the Porur-Vadapalani stretch until certain civil works are completed.

Chennai Metro Rail decided against opening the Poonamallee-Porur stretch alone, opting instead to launch services up to Vadapalani for greater commuter benefit. This has postponed the entire stretch's opening. As reported by The Hindu, the rain highlighted these persistent issues.

Articoli correlati

Flooded railway tracks in Pekalongan, Indonesia, with a train navigating shallow water amid disruptions to services.
Immagine generata dall'IA

Flood in pekalongan disrupts rail services

Riportato dall'IA Immagine generata dall'IA

Flooding in Pekalongan since early Saturday has submerged the rail line between Pekalongan and Sragi stations, forcing PT Kereta Api Indonesia (KAI) to reroute trains via the southern path. Several services were cancelled, while special locomotives were prepared to navigate water up to 10 centimetres above the rails.

Chennai Metro Rail has completed construction of 26 deck slabs in the Porur to Vadapalani section of corridor 4 under the upcoming phase II project, a key requirement for train services. This forms part of the first stretch from Poonamallee to Vadapalani via Porur, originally scheduled to open to the public in February but postponed.

Riportato dall'IA

Chennai Metro Rail's phase II tunnelling from Thiruvanmiyur to Taramani has been delayed until June due to a snag in the tunnel boring machine (TBM). The affected section is part of corridor 5 from Madhavaram to Sholinganallur.

Nairobi Water has confirmed resumption of supply to Buruburu Phases 1 and 2, Kariobangi South and North, Dandora, and parts of Mathare after repairing a flood-damaged transmission pipeline along Outering Road. Services were disrupted by recent floods affecting thousands of homes. The company stated the pipeline has been fully restored.

Riportato dall'IA

In response to the ongoing water contamination crisis in Indore's Bhagirathpura area—which has caused at least eight deaths and hundreds of illnesses from diarrhoea since late December 2025—the central government is providing financial and technical aid via AMRUT 2.0 schemes. Union Minister of State for Housing and Urban Affairs Tokhan Sahu shared these details in a Rajya Sabha reply on February 2, 2026.

La Linea 17-Ouro della monorotaia di San Paolo è stata inaugurata il 31 marzo 2026, collegando la stazione di Morumbi all'aeroporto di Congonhas nella zona sud, con 12 anni di ritardo rispetto alla promessa fatta per la Coppa del Mondo 2014. I test della Folha hanno riscontrato che l'autobus e i servizi di ride-hailing sono più rapidi della metropolitana da Piazza Sé all'aeroporto. Il governatore Tarcísio de Freitas ha annunciato un prolungamento verso Paraisópolis.

Riportato dall'IA

In the ongoing Indore water contamination crisis that has claimed at least 15 lives, Madhya Pradesh Chief Minister Mohan Yadav warned the Opposition Congress against politicizing the tragedy in Bhagirathpura. On January 15, coinciding with a High Court summons to the chief secretary, Yadav inaugurated Rs 800 crore projects to upgrade the city's drinking water infrastructure.

 

 

 

Questo sito web utilizza i cookie

Utilizziamo i cookie per l'analisi per migliorare il nostro sito. Leggi la nostra politica sulla privacy per ulteriori informazioni.
Rifiuta