EDSA rehabilitation to start on December 24

The long-delayed rehabilitation of EDSA will begin on Christmas Eve, December 24, after being stalled earlier this year. Public Works Secretary Vince Dizon said the project will be completed in eight months, significantly shorter than the previous two-year timeline. Reblocking works and asphalt overlay on the busway lanes will be carried out round the clock during the holiday break.

Public Works Secretary Vince Dizon announced that the EDSA rehabilitation will start on December 24, a Wednesday, and be completed within eight months. This is shorter than the original two-year plan. Reblocking works and asphalt overlay on the busway lanes will be conducted round the clock from 11 p.m. on December 24 until 4 a.m. on January 5, 2026, during the holiday period when traffic is expected to be lighter, according to Metropolitan Manila Development Authority (MMDA) Chairman Don Artes.

After January 5, road works will continue nightly from 10 p.m. to 4 a.m. The total project cost is P6 billion, lower than the previous P17 billion estimate. The Department of Public Works and Highways will use a new stone mastic asphalt technology, which provides stronger resistance to elements and heavy loads, improved skid resistance, better protection against water and moisture damage, and a longer maintenance life.

There will be no changes to the existing number coding scheme, although the MMDA had proposed an odd-even scheme to manage potential congestion. The project was originally set to begin on June 13, but President Ferdinand Marcos Jr. ordered its postponement days before the launch, stating that a better plan was needed to shorten the timeline to six months to a year. EDSA, notorious for heavy traffic in Metro Manila, stands to benefit from these improvements to enhance road quality.

Makala yanayohusiana

Crowd commemorating 40th EDSA People Power Revolution anniversary with protests against corruption, veterans and senators speaking.
Picha iliyoundwa na AI

People power at 40th anniversary: Revolution remains unfinished

Imeripotiwa na AI Picha iliyoundwa na AI

On the 40th anniversary of the EDSA People Power Revolution, protests and commemorations marked the day, as veterans and senators warned about the importance of history and the ongoing fight against corruption.

The Department of Public Works and Highways has reduced the EDSA rehabilitation project's budget to P5.8 billion from an original P17 billion, Public Works Secretary Vince Dizon said. The first phase finished early, with bidding for phase two underway this month. The revised plan aims to minimize traffic disruption in Metro Manila.

Imeripotiwa na AI

MANILA — Amid continued oil price hikes, traffic volume on EDSA fell by eight percent, the Metro Manila Development Authority said yesterday. The agency also exempted oil tankers and vehicles delivering basic commodities from truck bans and number coding schemes.

The Land Transportation Franchising and Regulatory Board (LTFRB) has issued special permits to 1,297 buses to handle the expected surge in passengers during Holy Week. LTFRB Chairman Vigor Mendoza II said the move ensures enough vehicles as Filipinos travel to provinces for religious observances. Government agencies are preparing for increased traffic and passenger volumes.

Imeripotiwa na AI

Wizara ya Uchukuzi imetoa sasisho jipya juu ya maendeleo ya miradi mitatu ya expressway zinazofanya km zaidi ya 700. Acting Secretary for Roads Gilbert Arasa alizungumza wakati wa mkutano wa juu na Chief of Staff Felix Koskei. Miradi hiyo inatarajiwa kupunguza msongamano na kuimarisha uchumi.

Jumanne, 31. Mwezi wa tatu 2026, 10:28:43

TransSec forecasts over 5M daily passengers for Holy Week

Jumatatu, 30. Mwezi wa tatu 2026, 20:22:46

Marcos opens Cavitex-C5 Southlink segment 3B

Ijumaa, 20. Mwezi wa tatu 2026, 12:36:54

PUVs, PUBs and freight services granted two-month toll discounts

Jumapili, 8. Mwezi wa tatu 2026, 18:21:07

Government readies P3.5 billion for transport subsidy

Jumapili, 8. Mwezi wa tatu 2026, 18:09:10

DepEd approves four-day workweek for non-teaching personnel

Jumatano, 4. Mwezi wa tatu 2026, 20:04:29

Egypt accelerates rehabilitation of Raml Tram to boost capacity, cut travel time

Jumapili, 1. Mwezi wa tatu 2026, 09:54:09

Senate pushes DPWH overhaul to curb corruption

Jumamosi, 21. Mwezi wa pili 2026, 09:16:34

Citizen-led infrastructure monitoring launched as new people power

Jumamosi, 21. Mwezi wa pili 2026, 02:39:20

Marking the 40th anniversary of EDSA People Power

Alhamisi, 19. Mwezi wa pili 2026, 04:48:01

Philippines marks 40th anniversary of EDSA People Power Revolution

Tovuti hii inatumia vidakuzi

Tunatumia vidakuzi kwa uchambuzi ili kuboresha tovuti yetu. Soma sera ya faragha yetu kwa maelezo zaidi.
Kataa