Committee of Ministers Rejects Claims and Upholds Approval of Projects Worth US$1.51 Billion

The Committee of Ministers rejected claims against two investment initiatives worth US$1.51 billion, maintaining their environmental qualification resolutions.

The Committee of Ministers met on Tuesday and rejected the claims filed against the HVDC Kimal–Lo Aguirre Electrical Transmission Line and the Copiapó River Fluvial Works in Tierra Amarilla. Both initiatives total US$1.51 billion in investment and retained their respective Environmental Qualification Resolutions.

The transmission line, developed by Conexión Energía, involves US$1.48 billion and will connect the regions of Antofagasta, Atacama, Coquimbo, Valparaíso and Metropolitana to transport renewable energy. The fluvial works project by the Ministry of Public Works, at US$30 million, aims to mitigate flood risks in the Copiapó River basin.

Energy Minister Ximena Rincón said the project will deliver cleaner and more affordable energy from the north to the central zone. Conexión Energía welcomed the decision and stated that the project is under construction as planned.

This was the seventh session of the committee during President Kast's administration. The Mataquito Transmisora project was not reviewed due to lack of time.

Awọn iroyin ti o ni ibatan

Illustration showing President Petro rejecting Odinsa's toll proposal, with a business leader criticizing the decision.
Àwòrán tí AI ṣe

Government rejects Odinsa toll proposal in Eje Cafetero

Ti AI ṣe iroyin Àwòrán tí AI ṣe

The National Infrastructure Agency rejected Odinsa's private initiative IP Conexión Centro, which included $7 trillion in investments. President Gustavo Petro defended the decision, while business leader Bruce Mac Master criticized it.

The Committee of Ministers confirmed environmental permits for three investment projects totaling US$2.828 million, including Chile's first industrial-scale green ammonia initiative.

Ti AI ṣe iroyin

The Second Environmental Tribunal clarified on Thursday its May 14 ruling that partially annulled the environmental qualification resolution for the project of Compañía Minera Doña Inés de Collahuasi.

The finance commission approved the core of president josé antonio kast’s reconstruction megaproject on thursday after 15 hours of debate. The progress leaves divisions in the christian democrats between deputies and senators, while the opposition plans to obstruct the process.

Ti AI ṣe iroyin

Opposition lawmakers announced plans to submit over two thousand amendments to the national reconstruction project pushed by President José Antonio Kast's government. The move drew accusations of legislative sabotage from the executive branch, while some opposition sectors distanced themselves from the strategy.

Colombia’s Mines and Energy Minister Edwin Palma defended his handling of the Air-e financial crisis—ongoing since early 2026 with $1.6 trillion in debts—and announced key steps: a targeted $8/kWh surcharge on high-income users, a Creg proposal for more energy contracting ahead of El Niño, and calls for structural reforms in the Caribbean region's electricity sector.

Ti AI ṣe iroyin

YPF signed a mandate letter with BID Invest to structure up to US$500 million in financing for road works in Neuquén.

 

 

 