Two contractors withdraw from Chennai T3 terminal project

Two contractors have exited the T3 International Terminal project at Chennai airport after completing just 40 per cent of the work. The project now has a revised deadline of December 2026.

Two contractors responsible for interior work have withdrawn from the T3 International Terminal project at Chennai airport. The project forms part of the phase II modernisation and covers an area of 2,20,972 square metres at an estimated cost of ₹2,467 crore.

Civil works remain on track according to Airports Authority of India officials, who review progress weekly. They stated that the most challenging phase has been completed and fresh bids have already been floated to replace the departed contractors.

The original completion target was 2022, but the project has faced repeated delays partly due to the COVID-19 pandemic. The first phase, known as T2, opened in 2023 while work on T3 began the following year.

Officials expressed confidence that the December 2026 deadline will be met. They noted that rising costs had made continued participation financially unviable for the two firms that left.

Related Articles

Firefighters extinguish blaze at Lagos airport's old terminal as police helicopter assists; facility reopens after flight diversions.
Image generated by AI

Lagos airport reopens after fire outbreak, 3 flights diverted

Reported by AI Image generated by AI

A fire outbreak at the old terminal of Murtala Muhammed International Airport in Lagos led to the diversion of three flights, but the airport has since reopened. Police deployed a helicopter to assist in managing the incident.

Chennai Metro Rail's phase II tunnelling from Thiruvanmiyur to Taramani has been delayed until June due to a snag in the tunnel boring machine (TBM). The affected section is part of corridor 5 from Madhavaram to Sholinganallur.

Reported by AI

Chennai Metro Rail's tunnelling work between Perambur Barracks and Purasawalkam has been delayed due to challenges in shaft construction and utility relocations. The 1.2 km stretch forms part of the larger phase II project.

CAF Asset Management Corp., through its Fondo de Deuda Senior para Infraestructura CAF-AM Ashmore II, granted a $300 billion credit to modernize and expand the Aeropuerto Internacional Rafael Núñez in Cartagena. This funding is part of a total $887 billion package with other banks and funds. The resources will renew over 25,000 square meters over the next five and a half years.

Reported by AI

The war in West Asia has driven up bitumen prices, slowing work on key road projects in Delhi, including the Barapullah Phase III elevated corridor. Public Works Department officials say supplies are intermittent due to shortages and cost hikes over the past month. Though the war has ended, its effects are expected to linger for months.

The Ethiopian Airlines Group and Ministry of Finance held high-level talks with the Bank of China over financing the $12.5 billion Bishoftu International Airport project. The April 1, 2026 meeting aims to strengthen the financial package, with the African Development Bank leading as arranger.

Reported by AI

A suspected fire involving IT cables at Cape Town International Airport led to a temporary halt in international flights on Tuesday. The Airports Company South Africa restored power by 6.30pm that evening. All passengers and staff remained safe throughout the incident.

 

 

 

This website uses cookies

We use cookies for analytics to improve our site. Read our privacy policy for more information.
Decline