Chennai metro rail tunnelling delayed by shaft construction issues

Chennai Metro Rail's tunnelling work between Perambur Barracks and Purasawalkam has been delayed due to challenges in shaft construction and utility relocations. The 1.2 km stretch forms part of the larger phase II project.

The work is part of corridor 3 in the 118.9 km phase II network, which runs underground from Madhavaram to Taramani before becoming elevated. Tunnelling on the upline began in September 2025 and has reached about 65 percent completion.

Officials cited delays in building the retrieval shaft at Purasawalkam junction after shifting utilities including water, sewer and power lines. The tunnel boring machine is operating at a depth of around 18 metres through weathered rock.

An official stated that the machine is expected to reach Purasawalkam in August. Construction of the shaft may require an additional three months, with full completion of this tunnel section scheduled for the end of November.

Related Articles

Rainwater leaking profusely from the ceiling of a Chennai Metro Rail Phase II station, with workers urgently repairing amid heavy downpour.
Image generated by AI

Rain exposes leakage issues in Chennai Metro Rail phase II stations

Reported by AI Image generated by AI

A sudden downpour on Monday morning exposed heavy leakages in some stations of Chennai Metro Rail's upcoming phase II project along the Poonamallee-Porur stretch. The issue has led to further postponement of the section's launch. Officials have initiated urgent repairs.

Chennai Metro Rail's phase II tunnelling from Thiruvanmiyur to Taramani has been delayed until June due to a snag in the tunnel boring machine (TBM). The affected section is part of corridor 5 from Madhavaram to Sholinganallur.

Reported by AI

Chennai Metro Rail has completed construction of 26 deck slabs in the Porur to Vadapalani section of corridor 4 under the upcoming phase II project, a key requirement for train services. This forms part of the first stretch from Poonamallee to Vadapalani via Porur, originally scheduled to open to the public in February but postponed.

Residents of Ambattur are voicing demands for a government hospital, wider roads, better rail access, and sewer networks amid stalled growth. These calls come ahead of the Tamil Nadu Assembly elections in the constituency. Local groups highlight traffic congestion, healthcare access, and lake pollution issues.

Reported by AI

The Greater Chennai Corporation has begun work on a pedestrian plaza along M.C. Road in North Chennai. The project, estimated at more than ₹24 crore, includes cobbled walkways and an underground storm-water drain network.

School Education Minister Anbil Mahesh Poyyamozhi seeks a hat-trick from Tiruverumbur in a multi-cornered contest. Voters express discontent over delays in service lanes along the Tiruchi-Thanjavur National Highway and recession in steel fabrication units. He has delivered projects like an Olympic Academy, jallikattu arena, and a government model school.

Reported by AI

The Greater Chennai Corporation plans to speed up biomining work at dump yards following an inspection by state officials on Saturday.

 

 

 

This website uses cookies

We use cookies for analytics to improve our site. Read our privacy policy for more information.
Decline