Chennai metro rail tunnelling delayed by shaft construction issues

Chennai Metro Rail's tunnelling work between Perambur Barracks and Purasawalkam has been delayed due to challenges in shaft construction and utility relocations. The 1.2 km stretch forms part of the larger phase II project.

The work is part of corridor 3 in the 118.9 km phase II network, which runs underground from Madhavaram to Taramani before becoming elevated. Tunnelling on the upline began in September 2025 and has reached about 65 percent completion.

Officials cited delays in building the retrieval shaft at Purasawalkam junction after shifting utilities including water, sewer and power lines. The tunnel boring machine is operating at a depth of around 18 metres through weathered rock.

An official stated that the machine is expected to reach Purasawalkam in August. Construction of the shaft may require an additional three months, with full completion of this tunnel section scheduled for the end of November.

Artikel Terkait

Rainwater leaking profusely from the ceiling of a Chennai Metro Rail Phase II station, with workers urgently repairing amid heavy downpour.
Gambar dihasilkan oleh AI

Rain exposes leakage issues in Chennai Metro Rail phase II stations

Dilaporkan oleh AI Gambar dihasilkan oleh AI

A sudden downpour on Monday morning exposed heavy leakages in some stations of Chennai Metro Rail's upcoming phase II project along the Poonamallee-Porur stretch. The issue has led to further postponement of the section's launch. Officials have initiated urgent repairs.

Chennai Metro Rail's phase II tunnelling from Thiruvanmiyur to Taramani has been delayed until June due to a snag in the tunnel boring machine (TBM). The affected section is part of corridor 5 from Madhavaram to Sholinganallur.

Dilaporkan oleh AI

Chennai Metro Rail has completed construction of 26 deck slabs in the Porur to Vadapalani section of corridor 4 under the upcoming phase II project, a key requirement for train services. This forms part of the first stretch from Poonamallee to Vadapalani via Porur, originally scheduled to open to the public in February but postponed.

Bogotá's Instituto de Desarrollo Urbano (Idu) announced that group 9 of avenue 68 has reached 80% progress, up from 32% in January. This 2.23 km section will enter its final phase this year, according to director Orlando Molano. The project includes lanes for TransMilenio and improvements to public spaces.

Dilaporkan oleh AI

The comprehensive sanierung of the railway line between Hamburg and Berlin is delayed due to the harsh winter. Deutsche Bahn states that the original completion date of April 30 cannot be met. A new timeline is to be announced on March 13.

Following last month's announcement of construction starting in March, the National Land Commission (NLC) has detailed fair compensation plans for over 3,500 landowners affected by the Naivasha-Kisumu-Malaba Standard Gauge Railway (SGR) phases 2B and 2C. NLC CEO Kabale Tache Arero highlighted the economic empowerment benefits, with public forums engaging stakeholders.

Dilaporkan oleh AI

Kenya's Transport Ministry has provided a fresh update on three major expressway projects spanning over 700 km. Acting Secretary for Roads Gilbert Arasa briefed Chief of Staff Felix Koskei during a high-level meeting. The initiatives aim to ease congestion and boost economic growth.

 

 

 

Situs web ini menggunakan cookie

Kami menggunakan cookie untuk analisis guna meningkatkan situs kami. Baca kebijakan privasi kami untuk informasi lebih lanjut.
Tolak