West Asia war raises bitumen costs, slows Barapullah III work in Delhi

The war in West Asia has driven up bitumen prices, slowing work on key road projects in Delhi, including the Barapullah Phase III elevated corridor. Public Works Department officials say supplies are intermittent due to shortages and cost hikes over the past month. Though the war has ended, its effects are expected to linger for months.

Road works under Delhi's Public Works Department (PWD), including repairs, new builds and the Barapullah Phase III elevated corridor, have slowed over the past month due to higher prices of petroleum products like bitumen, triggered by the West Asia war, PWD officials said.

The 3.5-km Barapullah Phase III extension of Phases I and II is 90% complete, with a revised June deadline. Officials noted intermittent supplies: "We received 20 tonnes yesterday, used today. Fifteen days ago, work stopped due to non-availability," one said on the project. Without regular bitumen, the deadline risks slipping.

Other affected works include strengthening 153 stretches over 400 km and repairing 128 stretches, with only 60 km done by the March 31 deadline. PWD has proposed extending it to July 31, pending Cabinet approval. Stretches like Bipin Chadrapal Marg to CR Park and Mathura Road are included.

Contractor Sudeer Nimesh, working in Trans-Yamuna areas like Sonia Vihar, said 80% of work has slowed, missing the March 31 target. Bitumen prices rose from Rs 40 per kg to Rs 65 since March. A senior PWD official expects resolution in three-four months, as "the war is over but its impact will linger." The project's cost has escalated from Rs 1,260.63 crore to Rs 1,635.03 crore, with further rises possible.

Artikel Terkait

Dramatic illustration of fiery oil tanker attack in Strait of Hormuz driving Brent crude prices over $100, with naval response, reserve releases, and India inflation impacts.
Gambar dihasilkan oleh AI

West Asia conflict surges oil prices past $100 per barrel

Dilaporkan oleh AI Gambar dihasilkan oleh AI

Brent crude oil prices have exceeded $100 a barrel amid Iranian attacks on commercial shipping and disruptions in the Strait of Hormuz. The International Energy Agency and the United States are releasing oil reserves to counter supply concerns. In India, the crisis is fueling inflation risks, higher agricultural input costs, and trade disruptions.

The West Asia war has disrupted supply chains, causing Nestlé India to face packaging shortages and a stockpile of Maggi noodles at one production unit. Bisleri has raised its 1-litre bottle price from Rs 18 to Rs 20. Automakers including Maruti Suzuki plan price hikes for small cars amid rising costs.

Dilaporkan oleh AI

Building on earlier concerns over GDP growth projections, the escalating West Asia war is pressuring Indian equity markets and disrupting footwear and textile sectors through supply shortages and cost spikes. Prashant Jain of 3P Investment Managers views the impact as marginal and transient, while industry reports show input costs up 10-50%.

The Batu-Negelle Arsi expressway, part of the Moyo Hawassa development project, is being constructed at a cost of 5 billion 39 million Birr and has reached 99% progress. This project forms part of the Addis Ababa-Moyo-Moyale-Lamu-Mombasa Trans International Highway.

Dilaporkan oleh AI

India’s goods trade deficit narrowed to $20.67 billion in March from $21.69 billion a year earlier, data from the Commerce and Industry Ministry showed. The easing came amid a West Asia crisis that curbed petroleum imports and exports to the region. Goods exports for FY26 rose 1% to $441 billion.

The Kochi Corporation has directed the Minor Irrigation department to postpone restoration work on the remaining 175-metre stretch of the Mullassery Canal until after the monsoon season. Mayor V.K. Minimol cited risks of severe civic disruptions if digging proceeds during peak rains. The ₹4.80-crore project was previously planned for completion within six to eight months using pre-cast technology.

Dilaporkan oleh AI

The US-Israel war in Iran is driving up construction material costs in Spain due to surging energy prices, prompting developers to anticipate higher new home prices. Experts forecast additional increases of 2 to 5 percentage points, depending on the conflict's duration. This adds to the 11.3% rise seen in 2025.

 

 

 

Situs web ini menggunakan cookie

Kami menggunakan cookie untuk analisis guna meningkatkan situs kami. Baca kebijakan privasi kami untuk informasi lebih lanjut.
Tolak