Chennai metro rail tunnelling delayed by shaft construction issues

Chennai Metro Rail's tunnelling work between Perambur Barracks and Purasawalkam has been delayed due to challenges in shaft construction and utility relocations. The 1.2 km stretch forms part of the larger phase II project.

The work is part of corridor 3 in the 118.9 km phase II network, which runs underground from Madhavaram to Taramani before becoming elevated. Tunnelling on the upline began in September 2025 and has reached about 65 percent completion.

Officials cited delays in building the retrieval shaft at Purasawalkam junction after shifting utilities including water, sewer and power lines. The tunnel boring machine is operating at a depth of around 18 metres through weathered rock.

An official stated that the machine is expected to reach Purasawalkam in August. Construction of the shaft may require an additional three months, with full completion of this tunnel section scheduled for the end of November.

संबंधित लेख

Rainwater leaking profusely from the ceiling of a Chennai Metro Rail Phase II station, with workers urgently repairing amid heavy downpour.
AI द्वारा उत्पन्न छवि

बारिश ने चेन्नई मेट्रो रेल के फेज II स्टेशनों में रिसाव की समस्या उजागर की

AI द्वारा रिपोर्ट किया गया AI द्वारा उत्पन्न छवि

सोमवार सुबह हुई अचानक बारिश ने चेन्नई मेट्रो रेल के आगामी फेज II प्रोजेक्ट के पूनमली-पोरुर खंड के कुछ स्टेशनों में भारी रिसाव की समस्या उजागर कर दी। इस घटना से इस खंड के उद्घाटन में और देरी हुई है। अधिकारियों ने तत्काल मरम्मत शुरू कर दी है।

Chennai Metro Rail's phase II tunnelling from Thiruvanmiyur to Taramani has been delayed until June due to a snag in the tunnel boring machine (TBM). The affected section is part of corridor 5 from Madhavaram to Sholinganallur.

AI द्वारा रिपोर्ट किया गया

चेन्नई मेट्रो रेल ने आगामी फेज़ II प्रोजेक्ट के कॉरिडोर 4 के पोरुर से वाडापलानी खंड में 26 डेक स्लैब का निर्माण पूरा कर लिया है, जो ट्रेन सेवाओं के संचालन के लिए एक महत्वपूर्ण आवश्यकता है। यह पहले स्ट्रेच पूनमallee से वाडापलानी होते हुए पोरुर के रास्ते का हिस्सा है, जो फरवरी में जनता के लिए खुलने वाला था लेकिन स्थगित हो गया।

Bogotá's Instituto de Desarrollo Urbano (Idu) announced that group 9 of avenue 68 has reached 80% progress, up from 32% in January. This 2.23 km section will enter its final phase this year, according to director Orlando Molano. The project includes lanes for TransMilenio and improvements to public spaces.

AI द्वारा रिपोर्ट किया गया

The comprehensive sanierung of the railway line between Hamburg and Berlin is delayed due to the harsh winter. Deutsche Bahn states that the original completion date of April 30 cannot be met. A new timeline is to be announced on March 13.

Following last month's announcement of construction starting in March, the National Land Commission (NLC) has detailed fair compensation plans for over 3,500 landowners affected by the Naivasha-Kisumu-Malaba Standard Gauge Railway (SGR) phases 2B and 2C. NLC CEO Kabale Tache Arero highlighted the economic empowerment benefits, with public forums engaging stakeholders.

AI द्वारा रिपोर्ट किया गया

Kenya's Transport Ministry has provided a fresh update on three major expressway projects spanning over 700 km. Acting Secretary for Roads Gilbert Arasa briefed Chief of Staff Felix Koskei during a high-level meeting. The initiatives aim to ease congestion and boost economic growth.

 

 

 