Judge orders Neiva city hall to pay $1.507 million for minor coliseum

A judge from the Second Administrative Court of Neiva ordered the city hall to pay $1,507,618,324 plus moratorium interest to Consorcio Atenas 121 for settling the construction contract of the Minor Volleyball Coliseum. The ruling settles a lawsuit after failed conciliation attempts and payment delays since the project handover in 2023. The consortium claims a lack of municipal willingness to settle the debt.

The Second Administrative Court of Neiva issued a payment order in favor of Consorcio Atenas 121 against Neiva city hall for $1,507,618,324, plus interest until full payment. This stems from contract No. 1139 of 2019 for building the Minor Volleyball Coliseum in Neiva, Huila, awarded for $8.2 billion during ex-mayor Rodrigo Lara Sánchez's administration. Work began in 2019 and was handed over two years after completion in 2023, overcoming initial design flaws such as soil issues, walls, fire protection network, Retie and Repilar updates, and RAS for water and sewer, requiring addendums and budget increases. Claudio Cesar Mejía Gutiérrez, the consortium's legal representative, explained that after filing the settlement and invoice dated December 27, 2023, and exhausting conciliations with the Attorney General's Office—where city hall expressed interest but provided no payment documents—they filed suit. The judge upheld the executive title with final receipt, termination, and bilateral settlement acts dated July 18, 2025. Juan Camilo Muñoz, Sports Secretary, said he was unaware of the lawsuit but that they are managing prompt payment, noting the debt as the remaining 10% of the contract and within timelines.

Artikel Terkait

AFA officials at new Pilar headquarters amid fund mismanagement investigations.
Gambar dihasilkan oleh AI

AFA confirms definitive settlement in Buenos Aires province

Dilaporkan oleh AI Gambar dihasilkan oleh AI

The Argentine Football Association (AFA) confirmed on Wednesday its change of address to Buenos Aires province, specifically to the Pilar district, placing it under the exclusive oversight of the Provincial Directorate of Legal Entities. This occurs amid investigations into alleged fund mismanagement, including documents found proving payments of at least 300 million pesos. The move has sparked controversy, with the General Inspection of Justice (IGJ) requesting overseers, though the AFA claims it has lost jurisdiction.

The criminal trial for irregularities in the remodeling of Neiva's Guillermo Plazas Alcid Stadium is on the brink of collapse due to judicial delays causing the prescription of several crimes. Accused interventors and contractors could be exonerated from lesser charges, leaving only embezzlement by appropriation intact. The 2016 tragedy, which killed four and injured ten, might end without convictions due to the passage of time.

Dilaporkan oleh AI

The trial over alleged corruption in Neiva's 2020 School Feeding Program (PAE) contracting moves forward with a new judicial timeline, led by Judge Olga María Erazo. Former mayor Gorky Muñoz Calderón, now a Senate candidate, faces charges alongside ex-officials and contractors. The preparatory hearing aims to wrap up evidence discovery to start the oral trial in March.

Spain's National Court has scheduled a trial for September 2027 against former Madrid regional vice president Ignacio González and four others for alleged contract rigging related to a golf course at the Canal de Isabel II. This case is part of the broader Lezo investigation, focusing on benefits gained by the politician's relatives between 2006 and 2012. Prosecutors seek six years in prison for González, while Madrid's regional government requests 16 years.

Dilaporkan oleh AI

The election of Neiva's municipal comptroller for the 2026-2029 period has faced multiple setbacks, including a candidate's resignation and a review of another's potential ineligibility. The process, involving interviews and voting, lacks a set date but could occur between December 16 and 17 if no further issues arise.

Supreme Court minister Diego Simpertigue defended his role in rulings linked to the Belarusian plot, as judicial fiscal suspended conservador Sergio Yáber for alleged ties. Deputy Cristián Araya faces claims of receiving payments, affecting José Antonio Kast's campaign. These developments highlight irregularities in a dispute between Consorcio Belaz Movitec and Codelco.

Dilaporkan oleh AI

The French state has paid 79 million euros to concessionaire Atosca to cover the 2025 halt of the A69 highway project. This judicially imposed pause disrupted the contract's economic balance. The environmentally contested initiative is slated for delivery in late 2026.

 

 

 

Situs web ini menggunakan cookie

Kami menggunakan cookie untuk analisis guna meningkatkan situs kami. Baca kebijakan privasi kami untuk informasi lebih lanjut.
Tolak