Firefighters battle blaze on cable bridge over Teltow Canal in Berlin, causing widespread power outage in southwest neighborhoods.
AIによって生成された画像

Major power outage in Berlin's southwest due to suspected arson

AIによって生成された画像

Since early Saturday morning, around 45,000 households and 2,200 businesses in Berlin's southwest have been without power, caused by a fire on a cable bridge over the Teltow Canal. Police are investigating arson, and a claim of responsibility is under review. Power restoration could take until Thursday, January 8, 2026.

The power outage started on Saturday morning, January 3, 2026, in Berlin's districts of Nikolassee, Zehlendorf, Wannsee, and Lichterfelde. Around 45,000 households and 2,200 businesses in the Steglitz-Zehlendorf district are affected. The cause is a fire on the cable bridge over the Teltow Canal to the Lichterfelde power plant, damaging several high-voltage cables. Police and the State Criminal Police Office (LKA) are investigating suspected arson; a claim of responsibility is being verified for authenticity by state protection authorities. Footprints in the snow have been secured, and witness tips are being sought.

Power grid operator Stromnetz Berlin estimates repairs, involving extensive excavation and the wintry weather with snow and cold, will take until Thursday afternoon. From Saturday evening, 10,000 households in Lichterfelde are to be supplied from alternative grids. The impacts are severe: Traffic lights, heating, internet, and mobile networks fail; supermarkets and restaurants close. In care homes and clinics, common in the aging region, residents must be evacuated; firefighters have already relocated patients from two facilities. Over 350 firefighters are deployed, supported by the Federal Agency for Technical Relief (THW). Emergency shelters and phone charging points have been set up, e.g., at Rathaus Wannsee and Mexikoplatz.

S-Bahn services are disrupted: Lines S1 (Zehlendorf-Wannsee), S7 (Charlottenburg-Potsdam), and regional trains RE1 and RE7 are partially out, with replacement buses running. Police advise via loudspeaker vans and social media to stay with relatives and assist vulnerable neighbors. An emergency doctor described the situation as 'war-like conditions.' The incident recalls a September 2025 outage in southeast Berlin affecting 50,000 customers, triggered by a politically motivated arson attack.

人々が言っていること

Reactions on X to the Berlin southwest power outage emphasize its scale, affecting 45,000-50,000 households until potentially January 8 amid cold weather. Users express concern for vulnerable groups like care home residents, describe dark streets and failing heating, and criticize infrastructure fragility. Speculation attributes it to left-wing extremism, referencing a similar September 2025 incident, while officials provide updates and aid points. Some call for community solidarity and better preparedness.

関連記事

Arson-damaged cable bridge over Teltow Canal in Berlin, claimed by anarchist Vulkangruppe group, causing major power outage; firefighters and police at scene.
AIによって生成された画像

Berlin power outage update: Anarchist group claims arson attack responsibility

AIによるレポート AIによって生成された画像

One day after an arson attack on a cable bridge over the Teltow Canal caused a major power outage in southwest Berlin, the left-extremist Vulkangruppe group has claimed responsibility, with authorities deeming the statement authentic. Governing Mayor Kai Wegner calls it terrorism. Partial reconnections are underway, but full restoration may take until Thursday.

In an update to the arson attack on a Berlin cable bridge claimed by the Volcano Group—which triggered the city's longest post-war power outage—the Federal Prosecutor's Office has assumed control of the probe. Suspected terrorist sabotage motives are under scrutiny as outages persist for over 25,000 households into day four.

AIによるレポート

Berlin's Governing Mayor Kai Wegner admitted playing tennis on the first day of a major power outage, while thousands suffered without electricity and heating. The incident, triggered by a suspected arson attack by left-extremist groups, has sparked sharp criticism and calls for his resignation. Wegner insists he remained reachable and continued working.

Over ten days after Storm Johannes struck on December 27, 2025, hundreds of households in Gävleborg remain without electricity amid prolonged outages exacerbated by a post-New Year snowstorm. Power company Ellevio intensifies restoration efforts as residents face ongoing cold, isolation, and uncertainty.

AIによるレポート

Three days after the extratropical cyclone triggered widespread blackouts in São Paulo—as previously reported—around 400,000 homes were still without power on December 13. Viral videos capture fleeting joys turned to despair, while protests and a court-mandated deadline pressure Enel amid ongoing restoration efforts.

Following the extratropical cyclone that struck São Paulo on December 10, over 1.3 million Enel customers remained without electricity by the evening of December 11. With no restoration timeline provided, authorities ramp up criticism of the utility and demand federal intervention.

AIによるレポート

As Storm Johannes continues to batter northern and central Sweden on December 27, 2025, power outages have expanded to affect up to 40,000 households, with new traffic warnings issued amid ongoing risks from falling trees. The storm has already claimed two lives, as previously reported, and is expected to abate overnight.

 

 

 