Last girder for LRT Jakarta Phase 1B installed above DDT Manggarai

PT Jakarta Propertindo completed installation of the final girder for the LRT Jakarta Phase 1B Velodrome-Manggarai route on Wednesday, July 8, 2026.

PT Jakarta Propertindo or Jakpro completed the lifting of the final girder above the Double Double Track area in Manggarai. That location was the most critical point because the LRT line sits directly above existing railway tracks with high operational intensity.

Jakpro chief executive Iwan Takwin said the DDT Manggarai area required careful planning and safety coordination so railway operations could continue uninterrupted. He called the spot the last critical point in the construction.

With the installation complete all girders along the Velodrome-Manggarai corridor are now connected 100 percent. Construction progress on LRT Jakarta Phase 1B reached 94.061 percent by the fourth week of June 2026.

Subsequent stages will focus on finishing follow-up works and strengthening operational readiness in line with the established target.

관련 기사

Illustration of Jakarta's improved transport and flood control under Governor Pramono Anung's leadership.
AI에 의해 생성된 이미지

Pramono focuses on improving Jakarta residents' comfort through connectivity

AI에 의해 보고됨 AI에 의해 생성된 이미지

DKI Jakarta Governor Pramono Anung stated his main focus is making capital residents' lives more comfortable through improved transport connectivity and flood control.

Jakarta Governor Pramono Anung Wibowo has opened the possibility of extending the LRT line to Soekarno-Hatta Airport. The move aims to improve public transport connectivity in the city's northern areas.

AI에 의해 보고됨

The Ministry of Public Works is accelerating construction of Phase II Sekolah Rakyat facilities to ensure they are ready for the 2026/2027 school year.

Head of Jakarta's transport agency Budi Awaludin said his office has prepared steps to address planned tariff adjustments for Transjabodetabek services.

AI에 의해 보고됨

President Prabowo Subianto established the Jakarta-Bandung High-Speed Rail Committee through Presidential Regulation Number 29 of 2026. He appointed Coordinating Minister for Infrastructure and Regional Development Agus Harimurti Yudhoyono as chair of the committee.

이 웹사이트는 쿠키를 사용합니다

사이트를 개선하기 위해 분석을 위한 쿠키를 사용합니다. 자세한 내용은 개인정보 보호 정책을 읽으세요.
거부