Boliden receives permit for continued operations at Aitik mine

The Land and Environment Court on Monday granted Boliden a permit for continued and expanded operations at the Aitik mine outside Gällivare.

The permit covers mining and processing of up to 45 million tons of ore per year. It includes measures such as raised dams and an expanded tailings storage facility.

The court imposed a large number of conditions regarding emissions to water and air, noise, dust control and consideration for reindeer herding. Boliden has operated the mine since 1968.

The case is not fully concluded. Boliden must carry out further investigations on certain issues. Financial security for remediation was set at approximately 6 billion kronor.

Makala yanayohusiana

Damaged underground tunnel in Garpenberg mine, closed until 2026 due to earthquakes, with cracks, debris, and warning barriers.
Picha iliyoundwa na AI

Parts of Garpenberg mine closed through 2026 after quakes

Imeripotiwa na AI Picha iliyoundwa na AI

Following a series of seismic events at the Garpenberg mine in Hedemora, Boliden announced that large parts of the mine will remain closed throughout 2026. The company expects to lose 70 percent of planned production and incur a 400 million kronor loss in the first quarter.

LKAB has received a new environmental permit for its operations in Malmberget. The permit covers both existing mining activities and plans for a demonstration plant producing iron sponge as part of the HYBRIT project.

Imeripotiwa na AI

Mining and smelting company Boliden reports strong first-quarter results, driven by higher metal prices and solid production. Abnormal seismic activity at the Garpenberg mine has caused a total production halt, set to impact volumes for the rest of the year.

Boliden has announced a 700 million kronor write-down of assets at the Garpenberg mine, damaged by seismic activity and a collapse in March that led to parts of the mine closing through 2026. The write-down covers infrastructure and equipment affected by the events.

Imeripotiwa na AI

The Second Environmental Tribunal clarified on Thursday its May 14 ruling that partially annulled the environmental qualification resolution for the project of Compañía Minera Doña Inés de Collahuasi.

Nuclear technology company Studsvik has submitted an application for state support to build reactors in Nyköping and Valdemarsvik. This is the third application for support for new nuclear power in Sweden.

Imeripotiwa na AI

Following the March 10 building permit for its planned data center in Horndal, Google Sweden has responded to key objections regarding electricity prices, job creation, and community benefits. Communications chief Joakim Larsson clarifies the project's status, as groundwork continues without a final business decision to build.

Jumapili, 17. Mwezi wa tano 2026, 18:04:15

Person trapped after rockfall in mine near Lycksele

Jumatatu, 11. Mwezi wa tano 2026, 01:20:04

No gunpowder factory in Borlänge – to be built in Kristinehamn

Ijumaa, 8. Mwezi wa tano 2026, 16:07:51

Land at Dikarbacken leased to private actor after 13 years

Jumatatu, 4. Mwezi wa tano 2026, 20:38:37

Boliden reveals situation in Garpenbergsgruva after collapse

Alhamisi, 23. Mwezi wa nne 2026, 22:08:22

Blasting resumes in Garpenberg mine after March collapse

Alhamisi, 16. Mwezi wa nne 2026, 20:55:28

Waste piles in Dannemora to be removed by landowner

Alhamisi, 9. Mwezi wa nne 2026, 09:18:43

Layoffs at Hedemora logistics firm follow Garpenberg mine halt

Alhamisi, 2. Mwezi wa nne 2026, 14:00:38

Garpenberg mine: Production cut to third of plan amid staff anxiety after collapse

Ijumaa, 20. Mwezi wa tatu 2026, 14:49:40

New details emerge on Garpenberg mine shaft expansion amid seismic issues

Alhamisi, 19. Mwezi wa tatu 2026, 19:49:39

New strong quake hits Garpenberg mine as Boliden meets locals

 

 

 

Tovuti hii inatumia vidakuzi

Tunatumia vidakuzi kwa uchambuzi ili kuboresha tovuti yetu. Soma sera ya faragha yetu kwa maelezo zaidi.
Kataa