CNMC opens 35 new sanction files against power firms for practices outside blackout

Spain's CNMC announced on Friday 35 new sanction proceedings amid the probe into the April 28, 2025 blackout, though these concern different days or periods. Iberdrola faces 18, Endesa 13, and Almaraz nuclear plant one very serious infraction. The regulator states these facts do not attribute the blackout's cause, which was multifactorial.

The CNMC has raised the total to 55 sanction proceedings after the first batch of 20 announced on April 17, which included one very serious case against Red Eléctrica (REE) and others targeting Iberdrola, Endesa, Naturgy, and Repsol facilities.

The new files mainly hit Iberdrola with 18, Endesa with 13—including Ascó and Vandellós nuclear plants—and one each to Engie, TotalEnergies, and Contour Global La Rioja. A standout is the very serious infraction against Centrales Nucleares Almaraz-Trillo, managed by Iberdrola, Endesa, and Naturgy, for alleged "reduction of production or supply without authorization" under article 64.37 of the Electricity Sector Law.

Most new cases involve serious infractions for failing voltage controls without supply risk, similar to last week's. The CNMC specifies these practices, uncovered in the probe, occurred on "days or periods other than April 28, 2025" and do not determine the blackout's cause.

Endesa CEO José Bogas told Congress on Monday that many probes date back two years before the incident and he anticipated more files. Business sources call the openings "forced and rushed," suggesting many may be archived.

Makala yanayohusiana

Dramatic illustration of Aneel initiating caducity process against Enel amid São Paulo blackouts from storms.
Picha iliyoundwa na AI

Aneel opens caducity process against Enel in São Paulo

Imeripotiwa na AI Picha iliyoundwa na AI

Brazil's National Electric Energy Agency (Aneel) decided on Tuesday (7) to open an administrative process to terminate the concession contract of distributor Enel in the São Paulo metropolitan region. The company has 30 days to defend itself before the agency issues an opinion to the Ministry of Mines and Energy, which has the final say. The action follows repeated blackouts caused by storms since late 2023.

Spain's CNMC has opened a very serious sanction file, dated April 23, against Iberdrola España and Iberdrola Generación Nuclear for possible unauthorized production cuts during the April 28, 2025 blackout—the third such case amid 56 total files opened recently in the ongoing investigation.

Imeripotiwa na AI

One year after the April 28, 2025, blackout that paralyzed power for 36 million consumers across Spain, Portugal, and parts of France, Spain's CNMC has escalated sanctions against Red Eléctrica and utilities including Endesa, Iberdrola, and Naturgy. Reinforced grid operations have spiked electricity costs, yet no structural reforms or political accountability have emerged.

Electricity company Enel announced scheduled power outages in several Metropolitan Region communes this Tuesday, March 17, to carry out maintenance work in specific areas. The disruptions will last a few hours in each sector.

Imeripotiwa na AI

Amid Cuba's deepening energy crisis, including the March 4 national power collapse, Etecsa has rationed internet and phone services with time slots due to outages and fuel shortages. Reports from multiple provinces highlight widespread disruptions and limited restorations.

Cuba will face prolonged blackouts this Sunday affecting 59% of its territory during peak energy consumption hours, according to the state-owned Unión Eléctrica (UNE). The crisis, worsened since mid-2024, has reached one of its worst points with impacts exceeding 60%. President Miguel Díaz-Canel blamed fuel shortages on U.S. pressures.

Imeripotiwa na AI

Enel Colombia has activated a contingency plan following a failure in the electrical infrastructure, worsened by extreme weather conditions, which disrupted power supply in El Colegio and surrounding areas in Cundinamarca. The company relocated about 50 crews and canceled scheduled work elsewhere to address the emergency. Around 150 technicians and operatives are currently working continuously on the progressive restoration of service.

Tovuti hii inatumia vidakuzi

Tunatumia vidakuzi kwa uchambuzi ili kuboresha tovuti yetu. Soma sera ya faragha yetu kwa maelezo zaidi.
Kataa