Koysha power plant completes first phase of concrete filling

The Koysha power plant project has completed the first phase of concrete filling for its powerhouse. Civil engineer Yitagesu Ayalew said construction proceeds in two 24-hour shifts. The dam now stands at 136 meters high.

Addis Ababa, July 21, 2026. The Koysha power plant project has completed the first phase of concrete filling for its powerhouse.

Civil engineer Yitagesu Ayalew said the project ranks third in Ethiopia's power development sector after the Grand Ethiopian Renaissance Dam and Gibe-3. Of the 7.725 million cubic meters of armata filling, more than 6.2 million cubic meters have been completed. Work proceeds around the clock in two shifts, averaging over 100,000 cubic meters per month.

The dam now reaches 623 meters above sea level, making its height 136 meters. For the spillway gates, 7.7 million cubic meters of excavation have been done, and structural armata filling stands at 45 percent complete.

The dam will house six turbines, each with 300 megawatts capacity. Electromechanical installation and all turbine components are in production. Local experts have benefited from technology and knowledge transfer during the project.

Makala yanayohusiana

The African Development Bank has approved up to $110 million to advance Ethiopia's largest wind power project. The funding supports the 300 MW Aysha facility in the Somali Region.

Imeripotiwa na AI

The long-interrupted construction of the 392-kilometre Awash Kombolcha Hara Gebeya railway project has resumed in Ethiopia.

Prime Minister Abiy Ahmed visited the construction site of the Gode Urea Fertilizer Factory. He said the project would finish soon and solve one of Ethiopia's key problems.

Imeripotiwa na AI

The Bishoftu Abusera International Airport project is under construction at a cost of 12.5 billion dollars. The first phase is scheduled for completion by 2030. The project aims to create jobs and increase foreign currency earnings.

Jumatano, 8. Mwezi wa saba 2026, 13:18:41

Bahir Dar International Stadium to Be Ready by September

Jumatatu, 6. Mwezi wa saba 2026, 11:55:46

Adama clean water project inaugurated at cost of 6.2 billion birr

Alhamisi, 25. Mwezi wa sita 2026, 22:22:03

Ethiopia signs 3 billion Birr agreement for power grid modernization

Jumanne, 23. Mwezi wa sita 2026, 06:55:10

Egypt reviews Dabaa Nuclear Power Plant progress

Jumamosi, 13. Mwezi wa sita 2026, 13:04:11

Ethiopia pushes to become Africa's renewable energy hub

Jumatano, 3. Mwezi wa sita 2026, 07:22:16

Ethiopia advances efforts to strengthen regional power interconnection

Jumamosi, 30. Mwezi wa tano 2026, 17:00:35

Prime minister Abiy calls for focus on 10.2 percent economic growth target

Jumanne, 26. Mwezi wa tano 2026, 08:22:22

Kenya in talks with Turkish firm for floating power plants

Jumamosi, 16. Mwezi wa tano 2026, 17:01:31

Minister reports progress on equitable infrastructure access

Ijumaa, 15. Mwezi wa tano 2026, 23:25:34

Hidroituango manager agrees to raise reservoir to maximum for El Niño

 

 

 

Tovuti hii inatumia vidakuzi

Tunatumia vidakuzi kwa uchambuzi ili kuboresha tovuti yetu. Soma sera ya faragha yetu kwa maelezo zaidi.
Kataa