Marcos Inaugurates Phase I of MTerra Solar Project

President Marcos inaugurated Phase I of the MTerra Solar Project in Gapan City, Nueva Ecija. The facility is described as the world’s largest operational integrated solar and battery storage project on a single site.

President Marcos inaugurated Phase I of the MTerra Solar Project yesterday in Gapan City, Nueva Ecija. He described the development as a major step toward strengthening the country’s renewable energy sector.

“This achievement comes at a time when the need to boost our energy sector has never been more apparent or more urgent,” Marcos said during the event. The project is developed by Terra Solar Philippines Inc., a joint investment between SP New Energy Corp. and Actis.

Phase I has energized 1,373 megawatts of solar photovoltaic capacity and is expected to become fully commercially operational by August. Phase II is targeted for completion in the first quarter of 2027. Once finished, the full facility is planned to deliver up to 3,500 MW peak of solar power supported by a 4,500-megawatt-hour battery system.

The completed project is expected to create thousands of jobs, reduce carbon emissions by around 4.3 million metric tons annually, and generate nearly P23 billion in financial benefits over the next decade.

Makala yanayohusiana

President Marcos Jr. shaking hands with Canadian executives over $2 billion investment deals in mining and IT sectors.
Picha iliyoundwa na AI

Marcos secures nearly $2 billion in Canadian investment pledges

Imeripotiwa na AI Picha iliyoundwa na AI

President Ferdinand Marcos Jr. ended his official visit to Canada with nearly $2 billion in investment commitments from Canadian firms focused on mining and IT-BPM sectors.

Hong Kong has launched a new solar farm on restored landfill in Tseung Kwan O. The facility, developed by Veolia, Sun Hung Kai Properties and Citic Pacific, is the largest of its kind in the city.

Imeripotiwa na AI

In last Friday's media briefing, two energy experts stressed the need for phased approaches and quick wins to realize the 100 GW solar program targeted for completion before 2029.

President Claudia Sheinbaum Pardo inaugurated the Central Ciclo Combinado González Ortega of CFE in Mexicali, Baja California, and stressed that energy production is a pillar of national sovereignty.

Imeripotiwa na AI

The PM Surya Ghar: Muft Bijli Yojana has installed rooftop solar systems in 40 lakh households so far. The target of 75 lakh households by year-end faces potential delays due to shortages of locally made panels.

Jumapili, 19. Mwezi wa saba 2026, 19:50:09

MinMinas reaches 4.63 GW in renewable energy

Ijumaa, 26. Mwezi wa sita 2026, 01:54:30

Marcos hastens SEA’s largest dialysis center

Jumamosi, 20. Mwezi wa sita 2026, 10:18:36

Marcos eyes nuclear energy partnership with Russia

Jumatatu, 15. Mwezi wa sita 2026, 14:25:15

MinMinas announces electrical interconnection with Venezuela from Vichada

Alhamisi, 28. Mwezi wa tano 2026, 08:03:05

Two mandals in Telangana to be developed as fully solarised

Jumanne, 19. Mwezi wa tano 2026, 14:29:44

Floating solar farm in Taiwan beats land-based rival

Tovuti hii inatumia vidakuzi

Tunatumia vidakuzi kwa uchambuzi ili kuboresha tovuti yetu. Soma sera ya faragha yetu kwa maelezo zaidi.
Kataa