2.4 billion birr project electrifies 21 new towns in Afar

Ethiopia's Electric Power utility is implementing a project costing over 2.4 billion birr to electrify 21 new towns in the Afar region, specifically in Afdera and Dalol areas. The initiative supports local cement and potash industries. Funding includes support from the African Development Bank.

The Ethiopian Electric Power (EEP) is overseeing a major electrification initiative in Ethiopia's Afar region. According to EEP communications head Anwar Abare, the project targets the cement and potash industries in Afdera and Dalol districts while connecting 21 emerging towns to the power grid.

Financing comes partly from the African Development Bank with 16 million dollars, while EEP covers the balance. The total cost exceeds 2.4 billion birr. Key components include 375 kilometers of medium-voltage lines, 93 kilometers of low-voltage lines, and 85 transformers.

To date, 27.8 percent of the medium-voltage work—34 kilometers—has been completed, along with 33 percent of low-voltage lines at 5 kilometers and 29 transformers installed. This has already brought electricity to eight centers and one factory. Ultimately, the project will serve 14,000 residents.

Overall progress stands at 84.46 percent, with completion slated for the current budget year. The effort bolsters mining activities, encourages private sector involvement in resource extraction, and stimulates the local economy.

相关文章

Deputy PM Temesgen Tiruneh cuts ribbon at Tendaho irrigation project inauguration with regional leaders, surrounded by green fields in Afar desert.
AI 生成的图像

Deputy PM Temesgen Tiruneh inaugurates rehabilitated Tendaho irrigation project

由 AI 报道 AI 生成的图像

Deputy Prime Minister Temesgen Tiruneh has inaugurated the rehabilitated and expanded Tendaho irrigation development project in Dubti woreda, Afar Region. Afar Region President Awel Arba and Water and Environment Minister Dr. Abraham Belay attended the event. The project has a capacity for 60,000 hectares, with 33,000 hectares now ready for irrigation.

Ethiopia's Electric Power has achieved 80% of its electrification development targets using domestic suppliers. This effort supports the green economy and expands local investment. Anwar Abare, head of communications, shared these details with Fana Digital.

由 AI 报道

The Ethiopian Electric Utility (EEU) has achieved certain targets even as the national grid faces ongoing challenges. The state-owned company inspected nearly half a million network issues and surpassed goals for transformer maintenance and installation. However, it fell short on meter installations and new voltage line constructions.

The Kenyan government plans to construct a Ksh375 billion gas-powered electricity plant at Dongo Kundu in Mombasa to boost national power supply. The project will rely on imported liquefied natural gas and support the Vision 2030 goal of clean energy production. Energy experts note the urgent need for more capacity amid economic growth and demands from large projects like data centres.

由 AI 报道

The Batu-Negelle Arsi expressway, part of the Moyo Hawassa development project, is being constructed at a cost of 5 billion 39 million Birr and has reached 99% progress. This project forms part of the Addis Ababa-Moyo-Moyale-Lamu-Mombasa Trans International Highway.

Egypt's presidency announced on Tuesday a plan to add 2,500 megawatts of renewable energy capacity to its national grid in 2026, aiming to bolster electricity stability and cut reliance on fossil fuels. The statement came after a meeting between President Abdel Fattah Al-Sisi, Prime Minister Mostafa Madbouly, and the ministers of electricity and petroleum.

由 AI 报道

Ethiopia's Minister of Planning and Development, Dr. Fitsum Assefa, stated that corridor development work is improving the living conditions of Arsi residents. Five residential buildings were inaugurated in Dara Wereda of the Sidama Region.

 

 

 

此网站使用 cookie

我们使用 cookie 进行分析以改进我们的网站。阅读我们的 隐私政策 以获取更多信息。
拒绝