South C collapse: Government confirms illegal extra floors by developers

In an update on the January 2, 2026, collapse of a 16-storey building in Nairobi's South C that killed at least two people, Lands and Housing CS Alice Wahome confirmed developers violated approvals by adding four unapproved floors to a structure cleared for 12 storeys. Rescue efforts retrieved one body, with investigations underway.

The collapse occurred on January 2 around 5 a.m. at Plot No. 209/5909/10 along Kiganjo Muhoho Avenue, prompting ongoing multi-agency rescues by Kenya Red Cross, National Disaster Management Unit, and National Police Service. The site remains cordoned off.

CS Wahome visited on January 5, revealing approvals covered only 12 storeys with construction up to the third floor at inspection. Developers illegally added four more floors. "At the time of the incident, the project was non-compliant on four additional floors that were never approved. That is the beginning of the problem, and our investigations will start from that point," she said.

A multi-sectoral team including the ministry, agencies, and professionals is probing violations, with threats of deregistration for culpable architects, contractors, and inspectors.

Nairobi Governor Johnson Sakaja stated the county issued non-compliance notices in May, July, and December 2025, ignored by developers. He urged prosecutorial powers for counties, citing ODPP inaction.

On January 4, DPP Renson Ingonga directed IG Douglas Kanja to investigate and report within seven days, including statements from developers, contractors, and officials. The ODPP emphasized rule of law and sympathies for victims.

Artículos relacionados

Rescue operations amid rubble after Verulam temple collapse, with emergency teams searching for trapped workers.
Imagen generada por IA

Templo de Verulam se derrumba, matando a un trabajador de la construcción

Reportado por IA Imagen generada por IA

Un templo de cuatro pisos en Redcliffe cerca de Verulam, al norte de Durban, se derrumbó el 12 de diciembre de 2025 mientras trabajadores añadían una estructura en la parte superior, resultando en una muerte confirmada y varios heridos. Las operaciones de rescate continúan mientras equipos buscan a otros atrapados bajo los escombros. El edificio carecía de planes aprobados, lo que lo hacía ilegal.

A 16-storey building under construction collapsed in Nairobi's South C on January 2, 2026, trapping at least two people. MPs have called for an immediate suspension of construction activities in the area amid concerns over safety regulations. Rescue operations are ongoing as authorities investigate the cause.

Reportado por IA

The Architectural Association of Kenya has detailed multiple regulatory failures preceding the collapse of a 14-storey building in South C on January 2, 2026. In their statement, they pointed to ignored stop orders and inadequate approvals. The group is urging investigations and tougher construction oversight.

After a deadly fire in Tai Po that claimed 168 lives, Hong Kong's government has proposed measures to strengthen building maintenance. Experts, however, warn that these pledges only scratch the surface of long-standing systemic issues in the sector.

Reportado por IA

Hong Kong police have expanded their probe into allegedly fake scaffolding net safety certificates to six estates, following discoveries at two sites after the Tai Po inferno that prompted the removal of mesh netting at about 200 locations last week. The blaze on November 26 killed at least 159 people, including a firefighter, and left nearly 5,000 homeless.

Un incendio que estalló el 9 de enero de 2026 en el asentamiento informal Site 5 en Du Noon, cerca de Ciudad del Cabo, destruyó casi 1.000 viviendas, desplazando a miles de residentes. La Ciudad de Ciudad del Cabo ha comenzado a registrar a los afectados para asistencia de socorro. Se están llevando a cabo esfuerzos para retirar escombros y apoyar la reconstrucción en medio de la crisis en curso.

Reportado por IA

A 43-hour blaze on November 26 devastated seven blocks at Hong Kong's Wang Fuk Court in Tai Po, killing at least 159 people and injuring 79. Preliminary investigations point to scaffolding between the first and second floors of one block as the likely starting point. As of December 7, 13 households remain uncontacted, with authorities not ruling out further deaths.

 

 

 

Este sitio web utiliza cookies

Utilizamos cookies para análisis con el fin de mejorar nuestro sitio. Lee nuestra política de privacidad para más información.
Rechazar