TEPCO's Kashiwazaki-Kariwa plant transmits power to Tokyo after 14 years

Tokyo Electric Power Company Holdings announced that its No. 6 reactor at the Kashiwazaki-Kariwa nuclear power station in Niigata Prefecture has begun transmitting electricity to the Tokyo metropolitan area for the first time in 14 years. The company conducted a grid connection test early Monday morning and started full-scale transmission in the evening. Commercial operations are scheduled for March 18.

Tokyo Electric Power Company Holdings, Inc. (TEPCO) revealed on February 18, 2026, that the No. 6 reactor at its Kashiwazaki-Kariwa nuclear power station in Niigata Prefecture has started transmitting electricity to the Tokyo metropolitan area, marking the first time in 14 years.

The company conducted a test connecting to the power grid at 2:55 a.m. on Monday, gradually increasing output to 20% or 270,000 kilowatts. Full-scale transmission began at 10 p.m. TEPCO plans to raise the reactor's output by 50%.

Later this month, the firm will halt the reactor to inspect for abnormalities from temperature or pressure changes, then restart it and increase output to full capacity. Commercial operation is expected to start on March 18, pending approval from the Nuclear Regulation Authority. According to TEPCO, the reactor can supply electricity to 3.75 million households if it operates stably for a month.

The No. 6 reactor was restarted on January 21 but halted on January 23 due to an alarm during control rod withdrawal, which regulates the nuclear chain reaction. After identifying the cause and implementing preventive measures, TEPCO restarted it on February 9. A neutron measuring device malfunctioned on February 12 but functioned properly on February 14 after parts replacement.

Artigos relacionados

Niigata Governor Hideyo Hanazumi announces restart of Kashiwazaki-Kariwa nuclear plant at press conference, with facility image projected behind.
Imagem gerada por IA

Niigata approves restart of world's largest nuclear plant

Reportado por IA Imagem gerada por IA

Niigata Governor Hideyo Hanazumi approved the restart of the world's largest nuclear plant, the Kashiwazaki-Kariwa facility, on Friday. This marks the first restart for operator TEPCO since the 2011 Fukushima disaster. The move supports Japan's goals to reduce fossil fuel reliance and achieve carbon neutrality.

Tokyo Electric Power Company Holdings (Tepco) began sending electricity from its Kashiwazaki-Kariwa nuclear plant in Niigata Prefecture to the Tokyo metropolitan area for the first time in about 14 years on Monday. The No. 6 reactor, restarted earlier this year, started generating and transmitting power at 10 p.m. Further inspections are planned ahead of potential commercial operations.

Reportado por IA

Tokyo Electric Power Company restarted its No. 6 reactor at the Kashiwazaki-Kariwa nuclear power plant in Niigata Prefecture on Wednesday evening. This marks TEPCO's first reactor restart since the 2011 Fukushima accident, though local residents remain divided. Commercial operations are slated for February 26.

A Comissão Reguladora Nuclear dos EUA concedeu à TerraPower permissão para iniciar a construção de seu reator nuclear inovador resfriado a sódio em Kemmerer, Wyoming. Respaldado por Bill Gates, o projeto Natrium marca a primeira aprovação desse tipo em quase uma década e visa integrar armazenamento de energia para maior compatibilidade com renováveis. A construção deve ser concluída até 2030, embora a licença de operação ainda esteja pendente.

Reportado por IA

Tokyo Electric Power Company Holdings unveiled a new robot arm on Wednesday for the project to remove nuclear fuel debris from its tsunami-crippled Fukushima No. 1 nuclear plant. The 22-meter-long arm can grab debris from a wider area than the previously used fishing rod-like devices. Tepco plans to begin setting it up next month and start the third trial at the No. 2 reactor this autumn.

Following the US Nuclear Regulatory Commission's approval for TerraPower's Natrium small modular reactor (SMR) in Wyoming, SK Innovation and Korea Hydro & Nuclear Power (KHNP) are expanding their collaboration on the project, leveraging their investments and expertise to build an SMR ecosystem for industrial applications like data centers.

Reportado por IA

Uma falha elétrica interrompeu os sistemas de refrigeração na Usina Nuclear de Chernobyl, na Ucrânia, levantando preocupações sobre riscos potenciais de radiação. No entanto, especialistas avaliam o perigo de derretimento como extremamente baixo devido ao estado envelhecido do combustível armazenado. A Agência Internacional de Energia Atômica está monitorando a situação de perto.

quarta-feira, 25 de fevereiro de 2026, 00:03h

Kashiwazaki-Kariwa No. 6 reactor restarts after scheduled halt

terça-feira, 17 de fevereiro de 2026, 07:50h

U.S. firm plans training hub for Fukushima debris removal by 2029

domingo, 15 de fevereiro de 2026, 00:30h

TEPCO fixes instrument glitch at Kashiwazaki-Kariwa nuclear plant

sábado, 24 de janeiro de 2026, 00:08h

Tepco suspends Kashiwazaki-Kariwa reactor restart after alarm

sábado, 17 de janeiro de 2026, 23:14h

Tepco reports alert system error at Kashiwazaki-Kariwa plant

quinta-feira, 15 de janeiro de 2026, 13:35h

Power outage halts major JR lines in Tokyo

segunda-feira, 12 de janeiro de 2026, 11:38h

KHNP to expand nuclear capacity factor to 15-year high

quarta-feira, 07 de janeiro de 2026, 15:21h

Japan halts Chubu Electric's Hamaoka nuclear restart screening

quarta-feira, 17 de dezembro de 2025, 04:23h

Akita Nairiku Line resumes services 4 days after train derailment

quinta-feira, 11 de dezembro de 2025, 19:22h

Over 40% of Japanese back nuclear plant restarts, poll shows

 

 

 

Este site usa cookies

Usamos cookies para análise para melhorar nosso site. Leia nossa política de privacidade para mais informações.
Recusar