New data centres to consume 34% of Cape Town's electricity supply

Four new major data centres in Cape Town are set to consume the equivalent of 34% of the city's current maximum electricity demand, raising sustainability concerns. Civil society groups have objected to Equinix's proposals over lacks in information on water, emissions and diesel generators. The city and Equinix responded that impacts are manageable.

Four major data centres are planned in Cape Town: Cavaleros Group's 360MW facility (thought to be linked to Microsoft, unconfirmed), Teraco's 60MW expansion, and Equinix's two centres with a combined peak demand of 160MW. Together, they would require 580MW, equating to over 34% of the City of Cape Town’s current maximum demand of 1,676MW.

The city did not comment on the calculation, citing Protection of Personal Information Act restrictions on customer data. A senior official noted that the additional demands are not significant in scale and could reinvigorate the grid.

Makala yanayohusiana

Protesters blocking data center construction sites across the United States in 2026.
Picha iliyoundwa na AI

Protests block 130 billion dollars in data center projects in early 2026

Imeripotiwa na AI Picha iliyoundwa na AI

Communities across the United States blocked or delayed at least 75 data center projects worth about 130 billion dollars from January through March 2026. Researchers described the period as the most blocked and delayed on record since tracking began in 2023. The opposition reflects a structural shift in local resistance to such developments.

A study warns that data centers may drive electricity bills higher in some US states. Increases could exceed 50 percent by 2030 due to growing demand.

Imeripotiwa na AI

A massive data center proposed for Imperial Valley, California, would require 750,000 gallons of water daily, raising fears among local residents about rising costs and shortages. Developer Sebastian Rucci plans to complete the 330-megawatt facility by 2028, but it faces lawsuits and regulatory hurdles. The project is one of 24 data centers set to open in the state by 2030.

Meta has agreed to fund seven new natural gas power plants and extensive energy infrastructure to support its largest data center under construction in Richland Parish, Louisiana. The deal with Entergy Louisiana includes 240 miles of transmission lines and battery storage, as reported by the Wall Street Journal. This follows a non-binding pledge by tech companies to cover power costs for AI data centers.

Imeripotiwa na AI

The country’s power grid struggled to fully meet peak daytime electricity demand for the first time this summer, with a shortage of 188 MW when demand hit a record 270 GW on Thursday.

Jumatano, 24. Mwezi wa sita 2026, 11:04:32

Tesla and Sunrun form 16 GW virtual power plant for data centers

Alhamisi, 4. Mwezi wa sita 2026, 11:13:48

Tech companies adjust data center cooling amid water concerns

Jumanne, 26. Mwezi wa tano 2026, 08:22:22

Kenya in talks with Turkish firm for floating power plants

Jumatatu, 18. Mwezi wa tano 2026, 19:04:03

Massive data center proposal in Utah draws backlash over environmental risks

Alhamisi, 14. Mwezi wa tano 2026, 09:07:55

Globe and PLDT report strong data center growth in Q1 2026

Jumanne, 28. Mwezi wa nne 2026, 17:54:40

Rural US communities resist data center expansion

Jumatano, 22. Mwezi wa nne 2026, 18:20:27

Gas-powered data centers could surpass Morocco's emissions

Alhamisi, 16. Mwezi wa nne 2026, 16:30:59

Maine legislature passes first US moratorium on large data centers

Jumatatu, 6. Mwezi wa nne 2026, 10:02:28

Tech firms pledge to offset data center energy costs

Ijumaa, 27. Mwezi wa tatu 2026, 05:29:26

AI data centres raise local land temperatures by up to 9.1°C

Tovuti hii inatumia vidakuzi

Tunatumia vidakuzi kwa uchambuzi ili kuboresha tovuti yetu. Soma sera ya faragha yetu kwa maelezo zaidi.
Kataa