Eskom publicly announced a stay on its legal challenge against Nersa's electricity trading licences, but court records show the case is proceeding. The discrepancy has raised questions about transparency in South Africa's energy sector reforms. Minister Kgosientsho Ramokgopa had urged restraint to support regulatory progress.

In mid-2025, Eskom launched a High Court review application in the Gauteng Division challenging the National Energy Regulator of South Africa's (Nersa) decision to grant electricity trading licences to five private companies: CBI-electric Apollo, Discovery Green, Green Electron Market, GreenCo Power Services, and NOA Group Trading. These licences, issued in 2024 and early 2025, align with the Electricity Regulation Amendment Act, 2024, aimed at fostering competition in the electricity market and reducing Eskom's monopoly.

Energy and Electricity Minister Kgosientsho Ramokgopa intervened in August 2025, publicly urging Eskom to withdraw or stay the litigation. He argued that ongoing court action could undermine Nersa's efforts to develop electricity trading rules, emphasizing the need for constructive engagement in the reform process.

On 30 September 2025, during its financial results presentation, Eskom CEO Dan Marokane stated that the company had placed a “stay” on the review application to allow Nersa's rule-making to proceed. Media reports portrayed this as a pause in response to the minister's calls, signaling cooperation.

However, a court directive dated 31 October 2025 reveals a different picture. It records that Eskom confirmed to the court it is proceeding with the application. The directive outlines active steps, including Eskom's response to a Rule 7(1) notice, drafting of confidentiality agreements, and preparation of the Rule 53 record by Nersa.

Eskom attributed the lack of a stay to the trader respondents, claiming they refused to agree and insisted on progression or abandonment. One trader denied ever being approached for a stay and noted the court was never informed of such a request. Another described Eskom's statements as factually incorrect or incomplete, pending internal processes.

This dual messaging—to the public and court—has eroded trust at a critical time. With Nersa public hearings on trading rules set for 27 January 2026, the ongoing litigation threatens investment and market confidence, hindering South Africa's shift toward a competitive electricity sector.

ተያያዥ ጽሁፎች

Collapsed transmission towers in Nelson Mandela Bay, South Africa, sparking amid power outages, with repair crews and affected residents in the dark.
በ AI የተሰራ ምስል

Transmission towers collapse in Nelson Mandela Bay causing outages

በAI የተዘገበ በ AI የተሰራ ምስል

Two transmission towers collapsed in Nelson Mandela Bay on Thursday, leading to widespread power outages and water disruptions affecting businesses and residents. The municipality is spending R10 million on repairs, with a revised 10-day restoration timeline. Community efforts have supported vulnerable individuals during the crisis.

South Africa's business landscape in 2025 started with optimism amid hopes for lower interest rates and stable governance, but quickly faced challenges from power stability gains to budget disputes and international trade pressures.

በAI የተዘገበ

South Africa's municipal electricity debt crisis extends beyond local governance failures to reveal deeper structural issues in the electricity distribution industry. Experts argue that dependency on Eskom, escalating tariffs since 2007, and uncompensated load shedding have trapped municipalities in a financial death spiral. This misalignment threatens economic reliability and competitiveness nationwide.

The Colombian government issued legislative decree 0044 on January 21, 2026, to ensure the continuity of electricity services amid an imminent crisis. The exceptional measures aim to bolster sector liquidity without impacting users or tariffs. Mines and Energy Minister Edwin Palma stressed the goal of preventing widespread blackouts in vulnerable areas like the Caribbean.

በAI የተዘገበ

The Nelson Mandela Bay metro council is set to hear a motion for the immediate suspension of more than 10 officials implicated in streetlight contract fraud. The proposal, submitted by DA councillor Ondela Kepe, follows revelations from Minister Velenkosini Hlabisa about a preliminary Special Investigating Unit report uncovering serious misconduct. It aims to address corruption that has left communities in darkness and heightened crime risks.

The Western Cape High Court has granted interim relief to LivPadel Knysna Hollow, halting a municipal decision to close its padel courts over noise complaints. The order suspends enforcement until a full review, allowing the facility to reopen during the peak holiday season. This development comes amid ongoing financial pressures on the Knysna Municipality.

በAI የተዘገበ

North West Premier Lazarus Mokgosi has denied claims of interfering in a municipal appointment, calling them part of a political smear campaign. He made these statements while testifying before a provincial committee investigating the allegations. The claims stem from a 2023 incident involving a report on a municipal manager's hiring.

 

 

 

ይህ ድረ-ገጽ ኩኪዎችን ይጠቀማል

የእኛን ጣቢያ ለማሻሻል ለትንታኔ ኩኪዎችን እንጠቀማለን። የእኛን የሚስጥር ፖሊሲ አንብቡ የሚስጥር ፖሊሲ ለተጨማሪ መረጃ።
ውድቅ አድርግ