68% of Anna Salai flyover completed amid delays

Nearly 68% of the 3.2 km flyover from Saidapet to Teynampet on Anna Salai has been completed. The project faces delays from war, elections and labour issues but aims for a September finish.

The State Highways Department reports slabs placed on girders for 1.1 km. Foundation work for pillars stands at 98% and 32 of 131 decks are in place. Eight more decks are targeted by the end of May.

The flyover crosses Metrorail tunnels, a unique aspect of the project. Thirteen of the 32 decks over the tunnels have been launched. The approach ramp on the Saidapet side and crash barriers are finished.

Delays stemmed from high fuel prices, war effects and labour shortages during elections. Workers have returned and officials expect completion on schedule in September.

At Teynampet and Nandanam stations, reinforcement bars along diaphragm walls have been tested. Twelve of 42 pedestals are ready. Local resident C. Sarathy called for temporary shelters at bus stops and measures to prevent water falling from the site.

Relaterte artikler

Rainwater leaking profusely from the ceiling of a Chennai Metro Rail Phase II station, with workers urgently repairing amid heavy downpour.
Bilde generert av AI

Rain exposes leakage issues in Chennai Metro Rail phase II stations

Rapportert av AI Bilde generert av AI

A sudden downpour on Monday morning exposed heavy leakages in some stations of Chennai Metro Rail's upcoming phase II project along the Poonamallee-Porur stretch. The issue has led to further postponement of the section's launch. Officials have initiated urgent repairs.

Chennai Metro Rail's tunnelling work between Perambur Barracks and Purasawalkam has been delayed due to challenges in shaft construction and utility relocations. The 1.2 km stretch forms part of the larger phase II project.

Rapportert av AI

Chennai Metro Rail's phase II tunnelling from Thiruvanmiyur to Taramani has been delayed until June due to a snag in the tunnel boring machine (TBM). The affected section is part of corridor 5 from Madhavaram to Sholinganallur.

The Kenya National Highways Authority has reported steady progress on the 740-kilometre Isiolo-Mandera Highway, setting a completion target of January 2028.

Rapportert av AI

School Education Minister Anbil Mahesh Poyyamozhi seeks a hat-trick from Tiruverumbur in a multi-cornered contest. Voters express discontent over delays in service lanes along the Tiruchi-Thanjavur National Highway and recession in steel fabrication units. He has delivered projects like an Olympic Academy, jallikattu arena, and a government model school.

São Paulo's Line 17-Ouro monotrilho was inaugurated on March 31, 2026, linking Morumbi station to Congonhas Airport in the south zone, 12 years late from its 2014 World Cup promise. Folha tests found bus and ride-hailing car faster than metro from Sé Square to the airport. Governor Tarcísio de Freitas announced an extension to Paraisópolis.

Rapportert av AI

The upgrade of Vasaloppsvägen between Oxberg and Fiskarheden will cost at least 150 million kronor more than planned. Extra costs have risen further over the winter. This now threatens other road projects in Dalarna.

 

 

 

Dette nettstedet bruker informasjonskapsler

Vi bruker informasjonskapsler for analyse for å forbedre nettstedet vårt. Les vår personvernerklæring for mer informasjon.
Avvis