68% of Anna Salai flyover completed amid delays

Nearly 68% of the 3.2 km flyover from Saidapet to Teynampet on Anna Salai has been completed. The project faces delays from war, elections and labour issues but aims for a September finish.

The State Highways Department reports slabs placed on girders for 1.1 km. Foundation work for pillars stands at 98% and 32 of 131 decks are in place. Eight more decks are targeted by the end of May.

The flyover crosses Metrorail tunnels, a unique aspect of the project. Thirteen of the 32 decks over the tunnels have been launched. The approach ramp on the Saidapet side and crash barriers are finished.

Delays stemmed from high fuel prices, war effects and labour shortages during elections. Workers have returned and officials expect completion on schedule in September.

At Teynampet and Nandanam stations, reinforcement bars along diaphragm walls have been tested. Twelve of 42 pedestals are ready. Local resident C. Sarathy called for temporary shelters at bus stops and measures to prevent water falling from the site.

Artigos relacionados

Night scene of the completed demolition of the Seosomun Overpass in Seoul with construction equipment and workers.
Imagem gerada por IA

Demolition of collapsed Seoul overpass completed

Reportado por IA Imagem gerada por IA

The Seoul city government said Friday that emergency demolition work on the upper structure of the Seosomun Overpass was completed at 9:40 p.m.

Chennai Metro Rail's tunnelling work between Perambur Barracks and Purasawalkam has been delayed due to challenges in shaft construction and utility relocations. The 1.2 km stretch forms part of the larger phase II project.

Reportado por IA

Interior Principal Secretary Raymond Omollo has announced that the Ngong Road-Naivasha Road flyover is complete. The project, built by KURA, cost Ksh3.58 billion and is set to ease traffic in Nairobi.

The Greater Chennai Corporation has begun work on a pedestrian plaza along M.C. Road in North Chennai. The project, estimated at more than ₹24 crore, includes cobbled walkways and an underground storm-water drain network.

Reportado por IA

The Centre has approved a 50 km eight-lane greenfield corridor linking Aroor and Angamaly. The project aims to ease congestion on existing routes around Kochi.

Preparatory work for the E22 bypass around Söderköping has begun after decades of planning. The road is expected to be completed in 2030 if the schedule holds.

Reportado por IA

School Education Minister Anbil Mahesh Poyyamozhi seeks a hat-trick from Tiruverumbur in a multi-cornered contest. Voters express discontent over delays in service lanes along the Tiruchi-Thanjavur National Highway and recession in steel fabrication units. He has delivered projects like an Olympic Academy, jallikattu arena, and a government model school.

quarta-feira, 08 de julho de 2026, 20:01h

Tamil Nadu plans 34 electricity substations for Chennai region

segunda-feira, 06 de julho de 2026, 16:20h

KURA attributes Kenyatta Avenue viaduct delay to complex engineering

segunda-feira, 22 de junho de 2026, 00:05h

Work begins on Vyttila Junction redevelopment project

quarta-feira, 10 de junho de 2026, 16:15h

Residents demand widening of CTH Road near Chennai

quarta-feira, 10 de junho de 2026, 00:01h

Bitumen costs delay bridge work on NH 48 in Ranipet

quinta-feira, 28 de maio de 2026, 22:21h

Southern railway opens new subway near ranipet

sábado, 16 de maio de 2026, 17:06h

Two contractors withdraw from Chennai T3 terminal project

sábado, 09 de maio de 2026, 10:14h

High-level group begins examining Chennai metro rail extensions

quinta-feira, 07 de maio de 2026, 06:50h

Kenya reports progress on Isiolo-Mandera highway project

terça-feira, 14 de abril de 2026, 19:44h

First section of new cycle bridge arrives at Slussen

 

 

 

Este site usa cookies

Usamos cookies para análise para melhorar nosso site. Leia nossa política de privacidade para mais informações.
Recusar