Construction begins on E22 bypass around Söderköping

Preparatory work for the E22 bypass around Söderköping has begun after decades of planning. The road is expected to be completed in 2030 if the schedule holds.

The Swedish Transport Administration has started soil investigations and forest clearing along the planned route. The E22 through Söderköping has long been one of the country’s most notorious traffic bottlenecks due to queues from traffic lights and bridge openings over the Göta Canal.

Project manager Andreas Eklund says construction traffic will increase. He adds that the agency aims for the road to be ready in summer 2030, though a case concerning the aqueduct at the Göta Canal is with the Land and Environment Court of Appeal.

Earlier proposals included bridges, tunnels and a boat lift over the canal. The final solution is an aqueduct. Actual road construction is scheduled to begin in the autumn.

Artigos relacionados

Traffic on E22 was closed late Friday evening between Kronetorp and Lund Norra to lift the first of two new green pedestrian and cycle bridges into place over the motorway in Lund. Work was delayed by darkness and cold but the bridge was in position by 22:00. Lund residents must wait until the end of June to use it.

Reportado por IA

Several road works and projects are underway in central Uppsala during summer 2026 and affect accessibility on multiple streets.

The upgrade of Vasaloppsvägen between Oxberg and Fiskarheden will cost at least 150 million kronor more than planned. Extra costs have risen further over the winter. This now threatens other road projects in Dalarna.

Reportado por IA

The government has presented the national plan for transport infrastructure 2026–2037. The investment totals 1,171 billion kronor with a clear focus on maintenance in Dalarna.

sábado, 04 de julho de 2026, 14:17h

Plan for new Forshuvudbron in Borlänge remains on track

quinta-feira, 02 de julho de 2026, 17:22h

Trafikverket targets 2036 opening for Lund-Hässleholm track

terça-feira, 30 de junho de 2026, 04:35h

New power line for 280 million planned

segunda-feira, 29 de junho de 2026, 03:26h

Sonesson pledges focus on infrastructure and commuting

quinta-feira, 25 de junho de 2026, 12:30h

New detailed plans adopted for Gottsunda

segunda-feira, 08 de junho de 2026, 00:31h

New pedestrian and cycle path between Uppsala and Björklinge completed

quarta-feira, 06 de maio de 2026, 05:20h

Two new bridges planned over Österdalälven near Oxberg

sexta-feira, 24 de abril de 2026, 06:18h

Uppsala municipality proposes detailed plan for Bergsbrunna station

terça-feira, 14 de abril de 2026, 19:44h

First section of new cycle bridge arrives at Slussen

domingo, 12 de abril de 2026, 23:16h

E16 between Hosjö and Hofors to get safer with smart animal warning systems

 

 

 

Este site usa cookies

Usamos cookies para análise para melhorar nosso site. Leia nossa política de privacidade para mais informações.
Recusar