68% of Anna Salai flyover completed amid delays

Nearly 68% of the 3.2 km flyover from Saidapet to Teynampet on Anna Salai has been completed. The project faces delays from war, elections and labour issues but aims for a September finish.

The State Highways Department reports slabs placed on girders for 1.1 km. Foundation work for pillars stands at 98% and 32 of 131 decks are in place. Eight more decks are targeted by the end of May.

The flyover crosses Metrorail tunnels, a unique aspect of the project. Thirteen of the 32 decks over the tunnels have been launched. The approach ramp on the Saidapet side and crash barriers are finished.

Delays stemmed from high fuel prices, war effects and labour shortages during elections. Workers have returned and officials expect completion on schedule in September.

At Teynampet and Nandanam stations, reinforcement bars along diaphragm walls have been tested. Twelve of 42 pedestals are ready. Local resident C. Sarathy called for temporary shelters at bus stops and measures to prevent water falling from the site.

Makala yanayohusiana

Rainwater leaking profusely from the ceiling of a Chennai Metro Rail Phase II station, with workers urgently repairing amid heavy downpour.
Picha iliyoundwa na AI

Rain exposes leakage issues in Chennai Metro Rail phase II stations

Imeripotiwa na AI Picha iliyoundwa na AI

A sudden downpour on Monday morning exposed heavy leakages in some stations of Chennai Metro Rail's upcoming phase II project along the Poonamallee-Porur stretch. The issue has led to further postponement of the section's launch. Officials have initiated urgent repairs.

Chennai Metro Rail's tunnelling work between Perambur Barracks and Purasawalkam has been delayed due to challenges in shaft construction and utility relocations. The 1.2 km stretch forms part of the larger phase II project.

Imeripotiwa na AI

Chennai Metro Rail's phase II tunnelling from Thiruvanmiyur to Taramani has been delayed until June due to a snag in the tunnel boring machine (TBM). The affected section is part of corridor 5 from Madhavaram to Sholinganallur.

The Kenya National Highways Authority has reported steady progress on the 740-kilometre Isiolo-Mandera Highway, setting a completion target of January 2028.

Imeripotiwa na AI

School Education Minister Anbil Mahesh Poyyamozhi seeks a hat-trick from Tiruverumbur in a multi-cornered contest. Voters express discontent over delays in service lanes along the Tiruchi-Thanjavur National Highway and recession in steel fabrication units. He has delivered projects like an Olympic Academy, jallikattu arena, and a government model school.

São Paulo's Line 17-Ouro monotrilho was inaugurated on March 31, 2026, linking Morumbi station to Congonhas Airport in the south zone, 12 years late from its 2014 World Cup promise. Folha tests found bus and ride-hailing car faster than metro from Sé Square to the airport. Governor Tarcísio de Freitas announced an extension to Paraisópolis.

Imeripotiwa na AI

The upgrade of Vasaloppsvägen between Oxberg and Fiskarheden will cost at least 150 million kronor more than planned. Extra costs have risen further over the winter. This now threatens other road projects in Dalarna.

Jumamosi, 23. Mwezi wa tano 2026, 04:02:47

Trees cut on Quirino Avenue for expressway project

Jumapili, 17. Mwezi wa tano 2026, 01:10:04

KURA announces two-week nightly closure on Ngong Road for flyover works

Jumamosi, 9. Mwezi wa tano 2026, 10:14:59

High-level group begins examining Chennai metro rail extensions

Alhamisi, 16. Mwezi wa nne 2026, 04:17:49

Transport ministry updates on three major expressway projects

Ijumaa, 10. Mwezi wa nne 2026, 16:31:19

Green bridge placed over E22 in Lund

Alhamisi, 9. Mwezi wa nne 2026, 23:47:29

West Asia war raises bitumen costs, slows Barapullah III work in Delhi

Alhamisi, 9. Mwezi wa nne 2026, 17:14:13

Noida International Airport prepares for first flights with gleaming interiors

Jumapili, 5. Mwezi wa nne 2026, 10:53:00

Ambattur residents demand hospital, roads, and sewer upgrades

Jumamosi, 28. Mwezi wa tatu 2026, 06:15:20

CMRL completes 26 deck slabs in Porur-Vadapalani corridor 4 section

Jumatano, 11. Mwezi wa tatu 2026, 12:19:05

Osaka metal pipe sinks to 1.6 meters after rising 13 meters

 

 

 

Tovuti hii inatumia vidakuzi

Tunatumia vidakuzi kwa uchambuzi ili kuboresha tovuti yetu. Soma sera ya faragha yetu kwa maelezo zaidi.
Kataa