Bogotá metro starts dynamic tests in workshop yard

Mayor Carlos Fernando Galán announced that the first three Bogotá metro trains are now conducting dynamic tests in the Bosa workshop yard. This milestone follows the electrification of the rail tracks, gearing up the system for up to 30 trains on the first line. Each train will complete 2,500 kilometers of tests in the city, mirroring those done in China.

The Bogotá metro has reached a key milestone with the start of dynamic tests for its first three trains in the Bosa workshop yard. Mayor Carlos Fernando Galán stated that this process is enabled by the completion of rail track electrification, through which up to 30 trains will run upon the first line's opening.

Each train already underwent initial tests in China, covering 2,500 kilometers before shipment to Colombia. Now in Bogotá, they will face similar trials, totaling another 2,500 kilometers. "The first Bogotá metro train already had 2,500 kilometers of tests in China before leaving for Colombia and here it must also complete 2,500 kilometers of testing; this is done initially in the workshop yard, with a conductor. This is a train that will operate automatically, as we have explained several times, but in these initial tests it does so with a conductor," assured Galán.

These initial tests are conducted with a driver in the workshop yard, though the system is designed for automatic operation. Train arrivals will continue progressively next year: the fourth train arrives on January 8, followed by one every 15 days, completing 30 by October. The workshop yard, with capacity for more than 30 trains in its 'hall de cocheras,' was built considering future expansions and additional unit acquisitions to bolster operations.

This progress marks a crucial step in the metro's construction, an iconic project to enhance mobility in Colombia's capital.

Labaran da ke da alaƙa

Mexico City Metro workers protest safety issues like fractured tracks during strike, impacting 2 million commuters.
Hoton da AI ya samar

Mexico City Metro workers stage staggered strikes over safety risks

An Ruwaito ta hanyar AI Hoton da AI ya samar

The National Union of the Collective Transport System Metro of Mexico City began staggered strikes on Monday, April 13, 2026, by not working overtime, leading to the loss of about 800 train runs and affecting nearly 2 million users. Union leader Fernando Espino highlighted severe issues like 7,000 fractured sleepers on Line 1 and lack of major maintenance on 70% of trains. President Claudia Sheinbaum stated there are no reasons for the strike, as resources are being invested in renovations.

Nuevo León government began tests of the Monterrey Metro Line 6 monorail on April 29, sparking social media criticism over its low speed and safety. Users question the project promised for the 2026 World Cup. Samuel García also faces reminders of an investigation into alleged resource diversion.

An Ruwaito ta hanyar AI

The Conpes 4190 document redefined financing for the Regiotram del Norte and excluded Bogotá from cofinancing, prompting objections from the mayor's office.

Authorities visited the factory assembling Chile's first hydrogen bus for the Red Movilidad fleet. The vehicle is set to be presented between August and September 2026 and enter service in early 2027.

An Ruwaito ta hanyar AI

Architect and urbanist Andrés Borthagaray highlighted extending Buenos Aires subway Line H to Sáenz as key to metropolitan connectivity. In an analysis for Canal E, he emphasized opportunities to enhance the current network and link it with trains like Belgrano Sur. The proposal aims to transform urban mobility in the region.