Fourth train arrives from China for Bogotá Metro Line 1 tests

The fourth train for Bogotá's Metro Line 1 has arrived at the Bosa workshop from Quingdao, China, following the start of dynamic tests on the first three trains. Mayor Carlos Fernando Galán announced the milestone, noting steady progress toward 90% completion by end-2026 and ongoing deliveries every 15 days until October.

Building on the dynamic tests already underway for the first three Bogotá Metro Line 1 trains at the Bosa workshop, the fourth train arrived in the early hours of Saturday from Quingdao, China—where it departed on December 3—after a journey of over a month.

Mayor Carlos Fernando Galán shared the update on his X account: "The Bogotá Metro keeps advancing: this morning, the fourth train for Line 1 arrived in our city... already at the Bosa workshop, where it will soon start tests."

As of late 2025, the project reached 70.72% completion, propelled by the first 10 kilometers of viaduct construction. Officials project 90% by year-end 2026, coinciding with dynamic tests for incoming trains. Deliveries will continue every 15 days through October, building toward a fleet of 30.

In December, Galán secured US$1,060 million in loans from the World Bank and Inter-American Development Bank to fund 2026 advances, reinforcing commitments to sustainable mobility in Colombia's capital.

Articoli correlati

President Sheinbaum cuts ribbon at inauguration of Mexico-Toluca 'El Insurgente' train after 12 years, crowd celebrates new 58km commuter line.
Immagine generata dall'IA

Treno México-Toluca entra in funzione dopo 12 anni di costruzione

Riportato dall'IA Immagine generata dall'IA

La presidente Claudia Sheinbaum ha inaugurato il 2 febbraio 2026 l'ultima fase del Treno Interurbano México-Toluca, noto come 'El Insurgente', un progetto iniziato nel 2014 con un investimento di 100 miliardi di pesos. Questa linea di 57,7 km collega Toluca all'ovest di Città del Messico, servendo oltre 230.000 passeggeri al giorno. Il progetto comprende sette stazioni e collegamenti con i sistemi Metro e Cablebús.

Mayor Carlos Fernando Galán announced that the first three Bogotá metro trains are now conducting dynamic tests in the Bosa workshop yard. This milestone follows the electrification of the rail tracks, gearing up the system for up to 30 trains on the first line. Each train will complete 2,500 kilometers of tests in the city, mirroring those done in China.

Riportato dall'IA

The Bogotá Metro project has advanced to over 70% completion as of early 2026, including a key milestone of 10 kilometers of viaduct constructed. Mayor Carlos Fernando Galán highlighted this progress, alongside the ongoing dynamic tests in the Bosa workshop, as the project enters its final stretch.

Una variazione nell'alimentazione elettrica esterna ha causato una sospensione temporanea del servizio sulla Linea A della Metro di Città del Messico. Le autorità hanno coordinato una rapida ripresa delle operazioni, e il servizio ora funziona normalmente. Il direttore della Metro ha ringraziato gli utenti colpiti per la loro comprensione.

Riportato dall'IA

Kamel Al-Wazir, ministro dei Trasporti e dell’Industria e vice Primo ministro per lo Sviluppo industriale, ha effettuato un giro di ispezione della fase uno della Linea 4 della metropolitana del Cairo, nell’ambito del monitoraggio governativo dei progetti nazionali di trasporto in linea con le direttive del presidente Abdel Fattah Al-Sisi. Il ministro ha visitato diverse stazioni lungo la sezione occidentale della fase uno, che si estende dal Grand Egyptian Museum a El-Fustat. Ha esaminato i progressi dei lavori civili e ha ordinato che il ripristino della superficie sia effettuato immediatamente dopo la costruzione in ogni stazione.

Un deragliamento del Tren Interoceánico a Nizanda, Oaxaca, il 28 dicembre 2025, ha lasciato 13 morti e 98 feriti, cinque in condizioni gravi. La Secretaría de Marina ha dispiegato un'ampia operazione di soccorso, mentre le autorità federali e statali coordinano le cure alle vittime. La presidente Claudia Sheinbaum ha ordinato supporto immediato alle famiglie colpite.

Riportato dall'IA

Claro Colombia presented its 5G network balance at the end of 2025, noting it captured 68.4% of national traffic for this technology. In 24 months, the company connected 50 cities and deployed over 2,200 base stations. It also progressed on 5G auction obligations, linking 233 rural educational institutions with fiber optics.

 

 

 

Questo sito web utilizza i cookie

Utilizziamo i cookie per l'analisi per migliorare il nostro sito. Leggi la nostra politica sulla privacy per ulteriori informazioni.
Rifiuta