Defunding foreign-assisted projects inflicts heavy costs on Philippines

Over four consecutive budget cycles from 2023 to 2026, hundreds of billions of pesos allocated for infrastructure projects like airports, railways, and flood control were stripped from the national budget. This led to idle loans, escalating costs, and harm to communities. According to a former budget secretary, this defunding did not save money but wasted it.

In 2023, the executive branch proposed ₱210 billion for foreign-assisted projects (FAPs), but ₱158 billion was removed during the budget approval process. For 2024, ₱246 billion was suggested, with ₱242 billion stripped away. In 2025, ₱216 billion was planned, but at least ₱118 billion was cut, and in 2026, ₱283 billion was proposed with ₱190 billion deprogrammed, including ₱93 billion vetoed by the president.

Overall, nearly ₱800 billion in projects were affected across four years. These initiatives, already approved and negotiated with institutions like the Asian Development Bank and World Bank, became unusable due to missing government counterpart funds and authorization. As a result, the government paid hundreds of millions of pesos in commitment fees for idle loans, while delays caused higher costs from rebidings and redesigns.

Butch Abad, former secretary of the Department of Budget and Management, stated, "Defunding foreign-assisted projects did not save money. It wasted it." Funds were redirected to smaller, locally controlled projects that offer quick political visibility but often prove substandard or ineffective, as revealed by investigations from the Senate blue ribbon committee and Independent Commission for Infrastructure. This erodes investor confidence, contributes to declining foreign direct investment, and disproportionately burdens poor communities facing floods and congestion.

While Congress bears primary responsibility for the removals, the executive faces criticism for insufficient defense of these projects. The outcome: stalled infrastructure, slowed growth, and systemic waste of public funds.

Artigos relacionados

President Marcos signs P6.793-trillion 2026 national budget, highlighting education and infrastructure allocations amid vetoes for prudent spending.
Imagem gerada por IA

Marcos signs P6.793-trillion budget for 2026

Reportado por IA Imagem gerada por IA

President Ferdinand Marcos Jr. signed the P6.793-trillion national budget for 2026 on January 5, allocating a record P1.015 trillion to the Department of Education and P530.9 billion to the DPWH. He vetoed P92.5 billion in unprogrammed appropriations, leaving P150.9 billion, while vowing prudent spending to curb corruption. The budget bars political involvement in aid distribution, though critics question the remaining funds.

Secretary Vince Dizon appealed to the bicameral conference committee to restore P45 billion in the Department of Public Works and Highways' 2026 budget. He argued that the Senate's reductions were based on flawed calculations regarding construction costs. Thousands of projects could be scaled back if the funding is not reinstated.

Reportado por IA

Despite lawmakers' earlier promises to eliminate unprogrammed appropriations, the bicameral conference committee agreed to restore them to nearly P243 billion, close to the House's proposal. This amount is slightly higher than the House's original P243.2 billion. The decision comes amid controversies over the funds' use.

A ministra sul-africana de Planeamento, Monitorização e Avaliação, Maropene Ramokgopa, anunciou que o governo alocou fundos significativos para melhorar a infraestrutura pública nos municípios. Um comité interministerial apoiará os governos locais em dificuldades. Isto faz parte do último relatório de progresso do Plano de Desenvolvimento a Médio Prazo.

Reportado por IA

Following yesterday's postponement, the bicameral conference committee on the 2026 budget delayed DPWH deliberations by four hours on December 16 due to private discussions resolving a deadlock. The session was deferred to the next day.

President Ferdinand Marcos Jr. signed the P6.793-trillion 2026 national budget into law on January 5, 2026, at Malacañang Palace, amid a major government corruption scandal. This marks the latest signing under his administration, leading to a reenactment of the 2025 budget until January 4. The budget emphasizes education, health, and anti-corruption reforms.

Reportado por IA

The bicameral conference committee for the 2026 national budget began on December 13, 2025, focusing on reconciling versions for education, health, and agriculture sectors. Discussions stalled over farm-to-market roads funding due to corruption concerns, but lawmakers eventually agreed to increase it. Meanwhile, a congressman resigned from the House contingent amid complaints against him.

sexta-feira, 30 de janeiro de 2026, 11:36h

President Marcos orders fast-tracking of infrastructure and classroom projects

sexta-feira, 16 de janeiro de 2026, 13:07h

CCI denuncia corte de US$ 1 bilhão em apropriações futuras para megaproyectos

segunda-feira, 12 de janeiro de 2026, 02:20h

DPWH to scrap Cabral's parametric formula for district budgets

quarta-feira, 07 de janeiro de 2026, 04:19h

Marcos vetoes P43.24 billion personnel services funding in 2026 budget

sábado, 03 de janeiro de 2026, 05:26h

Palace: 2026 national budget review nears completion

terça-feira, 30 de dezembro de 2025, 05:56h

Rep. Leviste details allegations on budget 'allocables' and 'incentives'

segunda-feira, 29 de dezembro de 2025, 12:29h

Palace begins review of 2026 national budget

sexta-feira, 19 de dezembro de 2025, 08:30h

DOH Rejects MAIFIP Funds Shift to PhilHealth Amid Budget Debates

quinta-feira, 18 de dezembro de 2025, 04:18h

Bicam approves higher AICS funding in 2026 budget

quinta-feira, 30 de outubro de 2025, 18:47h

Espina family in Biliran faces plunder complaint over DPWH projects

 

 

 

Este site usa cookies

Usamos cookies para análise para melhorar nosso site. Leia nossa política de privacidade para mais informações.
Recusar