EU subsidies probe forces China's CRRC out of Lisbon metro bid

China's railway giant CRRC has withdrawn from a Lisbon metro contract after a European Commission probe found billions in subsidies gave it an unfair edge. A Polish firm, PESA, will replace it in the Mota-Engil-led consortium. The bid totals €598.8 million for the Portuguese capital's new Violet Line.

China's CRRC has been ousted from a Lisbon metro contract after the European Commission confirmed that foreign subsidies allowed it to underbid rivals. The probe under the Foreign Subsidies Regulation (FSR) targeted CRRC Portugal's role as a subcontractor providing metro cars worth about €50 million.

"The in-depth investigation confirmed these preliminary findings, revealing that the subsidies in question had indeed given the consortium an unfair competitive edge, to the detriment of other bidders taking part in the tender and the integrity of the EU’s internal market," the European Commission said in a statement on Tuesday.

The Mota-Engil-led consortium, with the lowest bid of €598.8 million for constructing and maintaining Lisbon's new Violet Line, proposed replacing CRRC with Polish firm PESA, a change the Commission accepted to remove the distortion. The China Chamber of Commerce to the EU (CCCEU) voiced strong opposition, arguing the EU failed to explain why a subcontractor holding less than 10% of the contract warranted action.

Lisbon Metro launched the tender in April 2025, with Brussels opening its in-depth probe in November. After CRRC Portugal withdrew and refused to share group information, an anonymous EU official said the Commission pressed on, fearing a backdoor re-entry via unchanged prices and specs.

Relaterade artiklar

Illustration depicting EU's 'Made in EU' Industrial Accelerator Act proposal and China's warning of countermeasures amid trade tensions.
Bild genererad av AI

EU advances ‘Made in EU’ Industrial Accelerator Act; China warns of countermeasures

Rapporterad av AI Bild genererad av AI Faktagranskad

The European Commission has proposed the Industrial Accelerator Act, a flagship “Made in EU” initiative that would tie parts of public procurement and support schemes to local-content and low‑carbon requirements in selected strategic sectors. China’s commerce ministry has criticized the plan as discriminatory and warned it could respond if Chinese companies’ interests are harmed.

Portugal's Mota-Engil and China's CCCC, part of the winning consortium for the Santos-Guarujá tunnel, are staying silent amid a dispute between the federal and São Paulo state governments over project ownership. The companies await an agreement between the Lula and Tarcísio de Freitas administrations before construction begins in 2027. On Monday, representatives from both governments attended a signing ceremony for a R$ 2.57 billion loan from Banco do Brasil.

Rapporterad av AI

Spain's competition watchdog CNMC published a report on Friday recommending greater autonomy for Renfe and competitive tenders for commuter and medium-distance rail services before 2033.

Transport Minister Barbara Creecy has unveiled the draft National Rail Master Plan to revitalize South Africa's rail network. The plan, approved for gazetting by Cabinet on 1 April 2026, opened for public comment following consultations in Kempton Park. It aims to modernize freight and passenger services amid ongoing challenges at Transnet and Prasa.

Rapporterad av AI

Transport Minister Óscar Puente explains repair challenges for the Álora landslide that suspended the Madrid-Málaga AVE since February 4. Reopening is delayed until late April, impacting Easter Week and sparking disputes over economic loss figures. The PP criticizes the government and proposes an air bridge.

Santiago's RED public transport system annual subsidy reached a record US$1.274 billion in 2025 after four straight years of increases. Transport Minister Louis de Grange blames the previous administration's excessive bus purchases for creating surplus supply and historically low speeds.

Rapporterad av AI

Two days after TCU blocked R$ 2.6 billion in federal funding, São Paulo's government issued a decree opening supplementary credit of a similar amount for the Santos-Guarujá tunnel project. Governor Tarcísio de Freitas signed the document, supplementing the budget of the Secretariat for Partnerships in Investments. The step ensures the project's continuity, scheduled to start this year.

 

 

 