French state compensates Atosca with 79 million euros for A69 halt

The French state has paid 79 million euros to concessionaire Atosca to cover the 2025 halt of the A69 highway project. This judicially imposed pause disrupted the contract's economic balance. The environmentally contested initiative is slated for delivery in late 2026.

The A69 highway construction, linking Toulouse to Castres, was halted on February 27, 2025, by the Toulouse administrative court, which annulled the project's environmental permit. This new route, budgeted at 400 to 500 million euros, has faced strong opposition from environmental defense groups since its start.

Work resumed in late May 2025 following a provisional ruling by the Toulouse administrative court of appeal, upheld on the merits on December 30, 2025. The Council of State is now handling the case. The three-month interruption « disrupted the economic balance of the contract » between the state and Atosca, according to a transport ministry source.

After proceedings in the administrative court, mediation by two independent third parties led to a 79 million euro compensation, « almost halved » from Atosca's initial claims. This payment covers unforeseen additional costs from the stoppage, the ministry source explained. The ministry « deplores » the situation, blaming judicial challenges and « near-judicial obstruction by opponents ».

The opponents' group La voie est libre condemned the move, stating that « the state is a servile lackey bowing to NGE-Atosca and the A69 enforcers », denouncing an « organized system to give a private group its highway on public funds ». Atosca, in a statement, noted that « the site is fully mobilized, with delivery planned for the second half of 2026 ».

Revealed by investigative outlet Mediacités, this compensation increases the project's total budget by about 80 million euros.

Relaterade artiklar

Illustration showing President Petro rejecting Odinsa's toll proposal, with a business leader criticizing the decision.
Bild genererad av AI

Government rejects Odinsa toll proposal in Eje Cafetero

Rapporterad av AI Bild genererad av AI

The National Infrastructure Agency rejected Odinsa's private initiative IP Conexión Centro, which included $7 trillion in investments. President Gustavo Petro defended the decision, while business leader Bruce Mac Master criticized it.

Spain's Transport Minister Óscar Puente has unveiled a 1.629 million euro extraordinary plan to improve surfaces on state roads from 2027 to 2031. The initiative adds to the 1.800 million euros allocated annually for conserving the 26.500 km state road network. Puente acknowledged a structural deficit of 5.600 million euros in maintenance.

Rapporterad av AI

Portugal's Mota-Engil and China's CCCC, part of the winning consortium for the Santos-Guarujá tunnel, are staying silent amid a dispute between the federal and São Paulo state governments over project ownership. The companies await an agreement between the Lula and Tarcísio de Freitas administrations before construction begins in 2027. On Monday, representatives from both governments attended a signing ceremony for a R$ 2.57 billion loan from Banco do Brasil.

The Frei Paolino Baldassari Bridge collapsed on Friday night (5) in Sena Madureira, injuring four people. The state government announced it will sue Construtora Cidade.

Rapporterad av AI

The Second Environmental Tribunal clarified on Thursday its May 14 ruling that partially annulled the environmental qualification resolution for the project of Compañía Minera Doña Inés de Collahuasi.

Denna webbplats använder cookies

Vi använder cookies för analys för att förbättra vår webbplats. Läs vår integritetspolicy för mer information.
Avböj