French state compensates Atosca with 79 million euros for A69 halt

The French state has paid 79 million euros to concessionaire Atosca to cover the 2025 halt of the A69 highway project. This judicially imposed pause disrupted the contract's economic balance. The environmentally contested initiative is slated for delivery in late 2026.

The A69 highway construction, linking Toulouse to Castres, was halted on February 27, 2025, by the Toulouse administrative court, which annulled the project's environmental permit. This new route, budgeted at 400 to 500 million euros, has faced strong opposition from environmental defense groups since its start.

Work resumed in late May 2025 following a provisional ruling by the Toulouse administrative court of appeal, upheld on the merits on December 30, 2025. The Council of State is now handling the case. The three-month interruption « disrupted the economic balance of the contract » between the state and Atosca, according to a transport ministry source.

After proceedings in the administrative court, mediation by two independent third parties led to a 79 million euro compensation, « almost halved » from Atosca's initial claims. This payment covers unforeseen additional costs from the stoppage, the ministry source explained. The ministry « deplores » the situation, blaming judicial challenges and « near-judicial obstruction by opponents ».

The opponents' group La voie est libre condemned the move, stating that « the state is a servile lackey bowing to NGE-Atosca and the A69 enforcers », denouncing an « organized system to give a private group its highway on public funds ». Atosca, in a statement, noted that « the site is fully mobilized, with delivery planned for the second half of 2026 ».

Revealed by investigative outlet Mediacités, this compensation increases the project's total budget by about 80 million euros.

Artigos relacionados

Tense scene in French National Assembly as government weighs Article 49.3 or ordinance for 2026 budget amid deadlock with socialists.
Imagem gerada por IA

French government to choose between 49.3 and ordinance for 2026 budget

Reportado por IA Imagem gerada por IA

The French government, facing a parliamentary deadlock on the 2026 budget, must decide on Monday between article 49.3 and an unprecedented budgetary ordinance. It is renewing the surtax on large companies' profits at 8 billion euros, while renouncing a cut to the CVAE. This aims to secure an agreement with socialists to avoid censure.

A judge at the Toulouse correctional court has ordered Atosca to immediately suspend works on unauthorized zones along the A69 highway route between Toulouse and Castres. The ruling targets surrounding areas occupied by construction equipment and worker bases, while the main build can continue. Opponents hail it as acknowledging 10.7% of the project as legally off-limits.

Reportado por IA

Former businessman Jean-Michel Aulas, running for mayor of Lyon, unveiled in early January a plan for an 8-kilometer megatunnel to relieve congestion in the Fourvière tunnel. This proposal, aimed at easing car traffic, sharply divides the election campaign, pitting pragmatism against claims of self-interest. Critics argue it prioritizes private gains over alternative transport options.

Deputies in the Finance Commission overwhelmingly rejected Wednesday the state budget expenses for 2026, heavily rewritten with 27 billion euros in additional spending. This indicative vote highlights the lack of majority for the government text. Meanwhile, the Assembly approved a 2-euro tax on small extra-European parcels.

Reportado por IA

O governo colombiano confirmou um ajuste nas tarifas de pedágio efetivo em 16 de janeiro de 2026, vinculado à variação de 5.30% do Índice de Preços ao Consumidor. Isso se aplica a todas as concessões de rodovias e visa garantir a sustentabilidade financeira do sistema de transporte. Estratégias serão implementadas para aliviar o impacto nos usuários e transportadores.

O sindicato ATEPSA suspendeu a greve planejada para esta semana nos aeroportos argentinos após negociações com a EANA. O Ministério do Capital Humano confirmou a abertura de diálogo para resolver a disputa salarial. As operações aéreas normalizaram imediatamente, evitando cancelamentos.

Reportado por IA

A Agencia Nacional de Infraestrutura (ANI) confirmou que o projeto Devimed, Desenvolvimento Vial do Oriente Medellín, iniciará sua etapa de reversão entre 29 e 31 de julho de 2026. Esse processo terminará com a entrega formal da infraestrutura à Invías. Nos cinco meses anteriores, a concessionária permanecerá responsável pelas operações e manutenção.

quinta-feira, 05 de março de 2026, 21:07h

Eco-quarter project in Gruissan divides residents ahead of municipal elections

segunda-feira, 23 de fevereiro de 2026, 07:22h

Sarah Knafo's Paris program costing deemed haphazard

terça-feira, 17 de fevereiro de 2026, 02:12h

Hycsa vence contrato de 1.640 milhões de pesos para Linha 5 do Mexibús

quarta-feira, 21 de janeiro de 2026, 06:00h

Controlador alerta para riscos fiscais em mudanças no contrato do Canal del Dique

quarta-feira, 14 de janeiro de 2026, 00:31h

French assembly resumes debates on 2026 budget

quinta-feira, 08 de janeiro de 2026, 04:48h

France's 2026 budget returns to National Assembly commission

terça-feira, 06 de janeiro de 2026, 13:20h

Primeiros contratos assinados para concessões de rotas do corredor Mercosul

terça-feira, 30 de dezembro de 2025, 10:11h

O Ministério dos Transportes de Espanha aprova aumentos de portagens para 2026

quarta-feira, 17 de dezembro de 2025, 06:11h

Farmers block A61 near Carcassonne in escalating DNC protests

segunda-feira, 27 de outubro de 2025, 16:01h

French assembly starts debates on 2026 social security budget

 

 

 

Este site usa cookies

Usamos cookies para análise para melhorar nosso site. Leia nossa política de privacidade para mais informações.
Recusar