Court suspends unauthorized works on A69 highway

A judge at the Toulouse correctional court has ordered Atosca to immediately suspend works on unauthorized zones along the A69 highway route between Toulouse and Castres. The ruling targets surrounding areas occupied by construction equipment and worker bases, while the main build can continue. Opponents hail it as acknowledging 10.7% of the project as legally off-limits.

On January 12, a judge for freedoms and detention at the Toulouse correctional court issued a pivotal ruling in the dispute over the A69 highway. She orders Atosca, the project's lead contractor, to « immediately suspend ongoing and planned works outside the environmental authorization's designated area on identified sites along the A69 route ».

This follows stop-work orders from the prefects of Tarn and Haute-Garonne, who banned activities on these zones after the Toulouse prosecutor's request. The affected areas lie along the route's edges, used to store construction equipment and house worker camps without prior permits.

Nevertheless, the highway's core construction progresses in its final phase, upheld by an administrative appeals court decision from December 30. Atosca stated it will comply, describing the overrun as « temporary » and on bordering lands. The concessionaire has four days to rectify, facing a 20,000-euro daily fine for delays, per the prosecutor.

Agents from the French Office for Biodiversity (OFB) will verify the end of illegal occupation. At the January 19 hearing, prosecutors labeled these actions a « serious disturbance to environmental public order ». Opponents, who filed a complaint in late November over the encroachments, claim through lawyer Alice Terrasse that « 10.7% of the site is completely outside the legal framework ».

The A69 project, a symbol of ecological battles, faces ongoing challenges: opponents plan to appeal to the Council of State against the environmental permit. Atosca confirms works on the definitive route continue toward an autumn 2026 opening.

Artigos relacionados

The French state has paid 79 million euros to concessionaire Atosca to cover the 2025 halt of the A69 highway project. This judicially imposed pause disrupted the contract's economic balance. The environmentally contested initiative is slated for delivery in late 2026.

Reportado por IA

In Gruissan, in the Aude region, a project for 730 homes on a 32-hectare natural area is sparking intense tensions during the 2026 municipal election campaign. Promoted by Mayor Didier Codorniou, the development aims to address the housing crisis while promising a car-free seaside resort, but it endangers the ancestral vegetable gardens of 44 property owners.

Cerca de 2 mil pessoas protestaram neste sábado em Carrascosa del Campo, Cuenca, contra sete projetos de usinas de biogás na região de Campos del Paraíso. Os moradores denunciam os riscos de poluição por odores, transporte de resíduos e o uso de digestato em solos e aquíferos. A marcha contou com o apoio de 40 associações locais.

Reportado por IA

O juiz Santiago Pedraz, da Audiência Nacional da Espanha, arquivou o caso das ambulâncias, um desdobramento do caso 3% sobre o financiamento irregular da Convergència Democràtica de Catalunya (CDC). A decisão ocorre após três anos de investigação que não conseguiu provar irregularidades criminais em uma licitação de 2014. Os procuradores anticorrupção apoiam o arquivamento.

 

 

 

Este site usa cookies

Usamos cookies para análise para melhorar nosso site. Leia nossa política de privacidade para mais informações.
Recusar