Chennai Metro tunnelling from Thiruvanmiyur to Taramani delayed until June

Chennai Metro Rail's phase II tunnelling from Thiruvanmiyur to Taramani has been delayed until June due to a snag in the tunnel boring machine (TBM). The affected section is part of corridor 5 from Madhavaram to Sholinganallur.

Chennai Metro Rail's phase II project has hit a snag in tunnelling work between Thiruvanmiyur and Taramani due to a technical issue with the tunnel boring machine (TBM), delaying progress until June, as reported by The Hindu.

The 118.9-km phase II network comprises three corridors: corridor 3 from Madhavaram to SIPCOT, corridor 4 from Poonamallee to Light House, and corridor 5 from Madhavaram to Sholinganallur. The delayed section falls under corridor 5.

Construction of both elevated and underground structures has been ongoing for a couple of years. The Chennai Metro Rail Limited (CMRL) aims to enhance the city's transport infrastructure through this expansion.

관련 기사

Rainwater leaking profusely from the ceiling of a Chennai Metro Rail Phase II station, with workers urgently repairing amid heavy downpour.
AI에 의해 생성된 이미지

Rain exposes leakage issues in Chennai Metro Rail phase II stations

AI에 의해 보고됨 AI에 의해 생성된 이미지

A sudden downpour on Monday morning exposed heavy leakages in some stations of Chennai Metro Rail's upcoming phase II project along the Poonamallee-Porur stretch. The issue has led to further postponement of the section's launch. Officials have initiated urgent repairs.

Chennai Metro Rail's tunnelling work between Perambur Barracks and Purasawalkam has been delayed due to challenges in shaft construction and utility relocations. The 1.2 km stretch forms part of the larger phase II project.

AI에 의해 보고됨

Chennai Metro Rail has completed construction of 26 deck slabs in the Porur to Vadapalani section of corridor 4 under the upcoming phase II project, a key requirement for train services. This forms part of the first stretch from Poonamallee to Vadapalani via Porur, originally scheduled to open to the public in February but postponed.

As part of the ongoing rehabilitation of Mexico City Metro Line 2 for the 2026 World Cup—first announced in February—changes at Tasqueña station began on April 2. The south platform is out of service for floor replacement, with the north platform handling all boarding and alighting. Closures or restrictions also affected Viaducto, Chabacano, and San Antonio Abad stations amid Holy Week scheduling.

AI에 의해 보고됨

Minister of Transport Kamel Al-Wazir toured Alexandria to review progress on the rehabilitation and modernisation of the historic Raml Tram, a flagship national project aimed at upgrading urban mobility and easing traffic congestion in the coastal city. The 13.2-kilometre line, comprising 24 stations, will nearly triple its capacity and halve travel time once completed.

Nuevo León government began tests of the Monterrey Metro Line 6 monorail on April 29, sparking social media criticism over its low speed and safety. Users question the project promised for the 2026 World Cup. Samuel García also faces reminders of an investigation into alleged resource diversion.

AI에 의해 보고됨

The Delhi Metro Rail Corporation will operate 24 extra train trips every Monday starting May 18, 2026, using six additional trains to meet higher passenger demand.

 

 

 

이 웹사이트는 쿠키를 사용합니다

사이트를 개선하기 위해 분석을 위한 쿠키를 사용합니다. 자세한 내용은 개인정보 보호 정책을 읽으세요.
거부