NLC advances compensation for 3,500+ landowners in Naivasha-Kisumu-Malaba SGR extension

Following last month's announcement of construction starting in March, the National Land Commission (NLC) has detailed fair compensation plans for over 3,500 landowners affected by the Naivasha-Kisumu-Malaba Standard Gauge Railway (SGR) phases 2B and 2C. NLC CEO Kabale Tache Arero highlighted the economic empowerment benefits, with public forums engaging stakeholders.

Building on the February announcement that SGR phases 2B and 2C construction would begin in March 2026, the National Land Commission (NLC) and Kenya Railways are progressing with compensation for project-affected persons (PAPs). NLC CEO Kabale Tache Arero confirmed: “We are compensating over 1,000 affected by this project. Towards Kisumu, we are compensating over 3,500. Look at it in terms of economic empowerment.”

Over the past two months, public forums have involved communities, stakeholders, and PAPs. Land parcels are being identified, surveyed, valued, and compensated per land laws and market rates.

The project spans over 370 km: Naivasha-Kisumu (264 km, Phase 2B across nine counties, ending June 2027) with stations at Narok, Mulot, Bomet, Sotik, Sondu, Ahero, and 17 crossing stations; an 8.69-km branch to Kisumu Port; and Kisumu-Malaba (107 km, Phase 2C) with stations at Yala and Mumias, plus six crossing stations. It includes 13 tunnels, 23 bridges, and 376 culverts. Trains will operate at up to 120 km/h for passengers (1,096 capacity) and 80 km/h for freight (4,000 tonnes).

관련 기사

Nairobi Water technicians celebrate restored water supply to flood-hit estates after pipeline repairs.
AI에 의해 생성된 이미지

Nairobi Water resumes supply to six estates after pipeline repairs

AI에 의해 보고됨 AI에 의해 생성된 이미지

Nairobi Water has confirmed resumption of supply to Buruburu Phases 1 and 2, Kariobangi South and North, Dandora, and parts of Mathare after repairing a flood-damaged transmission pipeline along Outering Road. Services were disrupted by recent floods affecting thousands of homes. The company stated the pipeline has been fully restored.

Kenya's Motorists Association has warned that the Naivasha-Kisumu-Malaba railway extension will shift most cargo from roads to rail, weakening the highway-dependent economy.

AI에 의해 보고됨

Kenya's Treasury has allocated Ksh 40.25 billion for Standard Gauge Railway (SGR) and Meter Gauge Railway (MGR) projects in the 2026/27 budget. The funds aim to enhance connectivity, goods movement and economic growth. Several projects, including SGR Phase 2B and 2C, are already underway.

The Court of Appeal has directed the Kenyan government to release all documents related to the Nairobi-Mombasa Standard Gauge Railway project. The May 15 ruling dismissed an appeal by the Attorney General seeking to keep the contracts secret.

AI에 의해 보고됨

Nairobi City County has extended customer service centre hours this weekend to assist residents in paying land rates ahead of the April 1 crackdown. Governor Johnson Sakaja announced a 3% discount for payments made before March 31. The measure aims to boost compliance and revenue for public services.

The Kenya National Highways Authority has reported steady progress on the 740-kilometre Isiolo-Mandera Highway, setting a completion target of January 2028.

AI에 의해 보고됨

President William Ruto wrapped up his four-day tour of Luo Nyanza and Western Kenya counties on March 23, 2026, launching multi-billion-shilling development projects. The tour, which began with project approvals and opposition rebukes in Kisumu on March 20, is seen as challenging opposition and Linda Mwananchi efforts ahead of 2027 elections. Analysts warn that timely project completion could further weaken rivals.

 

 

 

이 웹사이트는 쿠키를 사용합니다

사이트를 개선하기 위해 분석을 위한 쿠키를 사용합니다. 자세한 내용은 개인정보 보호 정책을 읽으세요.
거부