港铁公司推进东涌西站工程项目

港铁公司宣布,东涌西站全长1.3公里的隧道将于今年9月完成挖掘。公司亦计划于明年上半年完成大部分主体结构工程。该车站位于东涌西部的逸东邨以西。

港铁公司周二表示,东涌西站工程进展顺利。铁路营运商在项目中采用了“半逆作法”施工。这种方法会先建造地面的顶板,以控制噪音和尘埃。

港铁公司大屿山项目交付主管李家亮指出,该方法允许地下挖掘和地面工程同步进行。他补充称,这是港铁首次在地下进行盾构机调头工作,无需将机器运回地面拆解及重新安装。

公司亦采用了多种施工技术,以进一步减少工程期间产生的噪音。新车站是东涌线延线项目的一部分。

相关文章

The Hong Kong government has approved handing three property sites to the future operator of a planned green transit system in East Kowloon to boost financial viability. The project linking Choi Hung and Yau Tong aims to open by 2033.

由 AI 报道

Hong Kong's Secretary for Development Bernadette Linn Hon-ho stated that no public subsidies will be required for the Pak Shek Kok MTR station project.

Chinese firm CRBC has been appointed main contractor for the Jabali Towers development at Tatu City on June 29.

由 AI 报道

Hong Kong's Airport Authority announced that the revamped Terminal 2 will open on May 27. Passengers will complete check-in, immigration and security at the new facility before moving to Terminal 1 for departures.

此网站使用 cookie

我们使用 cookie 进行分析以改进我们的网站。阅读我们的 隐私政策 以获取更多信息。
拒绝