Tram bridge case heads to Environmental Court of Appeal

Sweden's Environmental Court of Appeal has agreed to review the case for a tram bridge over the Fyris River in Uppsala. The municipality, which appealed a prior rejection, views the decision positively as it advances city development under the Quadruple Track Agreement.

Uppsala municipality has been pushing for a tram bridge over the Fyris River as part of a larger tram project aimed at linking the city's southeastern and southwestern areas with the planned train station in Bergsbrunna. Earlier this year, the Environmental Court rejected the application, deeming it deficient. The municipality immediately appealed to the higher Environmental Court of Appeal, which has now announced that the case will proceed to a main hearing.

Project leaders welcome the decision. "It was a welcome piece of news. The bridge is crucial for developing Uppsala in line with the Quadruple Track Agreement. Therefore, it is important that we get to show the Environmental Court of Appeal how we plan to build it with full consideration for the surrounding environment," says Felicia Johnson, lead project manager for the tram project.

According to municipal director of urban planning Christian Blomberg, the initiative focuses on long-term sustainability. "The tram is an investment in Uppsala's future. The application now under further review is about enabling the connection between Uppsala's southeastern and southwestern parts and the new train station to be built in Bergsbrunna. It will bring benefits for business, sustainability, and more housing in a growing city," he emphasizes.

The project is expected to improve public transport and support more housing in an expanding city, though it has faced opposition due to environmental concerns.

Artigos relacionados

Centerpartiet politician announces partial support for Uppsala tram project at construction site.
Imagem gerada por IA

Centerpartiet partially reverses stance on Uppsala tram project

Reportado por IA Imagem gerada por IA

Centerpartiet has partially reversed its opposition to Uppsala's tram project, now favoring construction of half the route rather than canceling it entirely. The decision stems from estimated cancellation costs of 3.8 to 4.2 billion kronor. Oppositionsråd Ehsan Nasari (C) stated that scrapping the whole project is no longer economically defensible.

Uppsala municipality has prepared a detailed plan for the new railway station in Bergsbrunna south of the city. The planning and building committee decided on Thursday to send the plan for consultation starting May 8. The station is set to handle 30,000 passengers per day when it opens in 2034.

Reportado por IA

The Swedish government has approved the expansion to four railway tracks between Uppsala and Stockholm. The decision removes the last remaining doubts about the project, aligning with the 2017 four-track agreement. The national plan secures funding for completion by 2034, including new stations.

Uppsala municipality has started controls to ensure valid documents and compliance with laws in its building projects.

Reportado por IA

Stockholm Chamber of Commerce has sharply criticized Trafikverket in a new report on Sweden's infrastructure development. The report highlights skyrocketing costs, slow bureaucracy, and reduced efficiency. Trafikverket, headquartered in Borlänge, dismisses the criticism as based on misunderstandings.

Traffic on E22 was closed late Friday evening between Kronetorp and Lund Norra to lift the first of two new green pedestrian and cycle bridges into place over the motorway in Lund. Work was delayed by darkness and cold but the bridge was in position by 22:00. Lund residents must wait until the end of June to use it.

Reportado por IA

The government has presented the national plan for transport infrastructure 2026–2037. The investment totals 1,171 billion kronor with a clear focus on maintenance in Dalarna.

segunda-feira, 08 de junho de 2026, 00:31h

New pedestrian and cycle path between Uppsala and Björklinge completed

quinta-feira, 04 de junho de 2026, 22:41h

Uppsala Municipality ties Peab and JM to Uppsala Södra development

sexta-feira, 22 de maio de 2026, 21:53h

Uppsala summer streets nearly ready with new olive trees

quinta-feira, 21 de maio de 2026, 05:58h

Tullgarnsbron stuck in raised position in Uppsala

quarta-feira, 06 de maio de 2026, 05:20h

Two new bridges planned over Österdalälven near Oxberg

segunda-feira, 04 de maio de 2026, 20:34h

Uppsala finalist for Sweden's Climate City of 2026

quarta-feira, 22 de abril de 2026, 01:24h

Naming committee names new bridge Sofielundsbron

terça-feira, 14 de abril de 2026, 19:44h

First section of new cycle bridge arrives at Slussen

quinta-feira, 09 de abril de 2026, 19:53h

Liberal Party's new Uppsala leader on SD and tramway

terça-feira, 17 de março de 2026, 05:56h

Barcelona city council approves tram connection on Diagonal

 

 

 

Este site usa cookies

Usamos cookies para análise para melhorar nosso site. Leia nossa política de privacidade para mais informações.
Recusar