Auditors flag delays and cost overruns in Clark air traffic control tower project

State auditors have flagged the P290.3-million New Clark Air Traffic Control Tower project for repeated extensions and cost increases, leaving it unfinished without a target completion date.

The P290.3-million New Clark Air Traffic Control Tower project was awarded in January 2021 with an expected completion within one year. A 2024 audit report by the Commission on Audit (COA) on the Clark International Airport Corporation (CIAC) revealed it has been extended six times, adding 930 days to the original 365-day contract, yet only 91% complete as of 2024. Costs have risen 22% to P354.41 million.

Auditors attributed delays to weak procurement planning, poor project monitoring, and possible shortcomings in the contractor's capacity. Groundbreaking occurred without required building, electronic, electrical, mechanical, plumbing, and sanitary permits from the Clark Development Corporation (CDC), the regulator for the Clark Freeport Zone. Under the National Building Code, such permits are mandatory, with penalties up to P20,000 fines or two years imprisonment.

"It was only on April 29, 2024 that CIAC was able to secure the necessary permits from the CDC. The absence of necessary permits during the construction period raises serious concerns regarding regulatory compliance, project authorization, and risk management," the report stated.

The contractor requested a suspension of the height clearance limit on March 17, 2022—two months after the original January 2022 completion date—after the Civil Aviation Authority of the Philippines (CAAP) denied permits for exceeding the 192-meter limit, with the tower's proposed top elevation at 228.81 meters (36.81-meter excess). An aeronautical study costing P3.9 million was submitted to CAAP on October 11, 2023, but the permit remains unissued as of December 31, 2024.

Additionally, installed elevators did not match the billed brand; a Global Fuji (Chinese) was found instead of the specified Schneider (German), approved by CIAC's then president during a March 20, 2025 inspection.

"Securing permits is a fundamental requirement in the construction industry, and failure to do so casts doubt on the contractor’s capability to manage regulatory requirements effectively," the report added, highlighting deficiencies in due diligence.

Awọn iroyin ti o ni ibatan

Realistic illustration of a press conference announcing charges against senators in a flood control kickback scandal, with documents and public frustration depicted.
Àwòrán tí AI ṣe

ICI recommends charges against senators in flood control scandal

Ti AI ṣe iroyin Àwòrán tí AI ṣe

The Independent Commission for Infrastructure has recommended criminal and administrative complaints against Senators Joel Villanueva and Jinggoy Estrada, former Representative Zaldy Co, and three others over alleged kickbacks in flood control projects. Related probes include a forged affidavit by a Senate witness linked to Co and efforts to forfeit implicated assets. Lawmakers are pushing for a stronger anti-corruption body amid public frustration with the inquiry's pace.

The Architectural Association of Kenya has detailed multiple regulatory failures preceding the collapse of a 14-storey building in South C on January 2, 2026. In their statement, they pointed to ignored stop orders and inadequate approvals. The group is urging investigations and tougher construction oversight.

Ti AI ṣe iroyin

The debate over Mexico's New International Airport (NAIM) in Texcoco has reignited after a hydraulic engineer claimed the project's design included flood prevention measures. Aviation experts called for reviving the build at a recent forum. This challenges the 2018 cancellation arguments.

Ombudsman Jesus Crispin Remulla said the Independent Commission for Infrastructure (ICI) might last only a month or two. However, ICI Chair Andres Reyes Jr. countered that the commission is set for two years of operation. The controversy stems from recent statements about the commission's powers and future.

Ti AI ṣe iroyin

The Bureau of Internal Revenue (BIR) has filed tax evasion complaints against Mark Arevalo, owner of Wawao Builders, over a P48.39 million tax deficiency from a non-existent flood control project in Malolos, Bulacan. The P77.20 million project received P72.37 million in payments, yet no structure was built despite claims of 100% completion. This marks the 13th such complaint by the BIR, with total potential tax liabilities reaching P8.92 billion.

Nigeria's domestic air traffic is set to face disruptions in 2026. The Air Traffic and Services Senior Staff Association of Nigeria (ATSSSAN) has urged the federal government to review navigational charges imposed by the Nigerian Airspace Management Agency (NAMA). This call highlights ongoing concerns in the aviation sector.

Ti AI ṣe iroyin

Spanish firm Indra has secured a nearly 300 million euro contract from the US Federal Aviation Administration to upgrade air traffic control systems. The deal aims to replace obsolete radars and enhance flight safety. It complements a similar project awarded to US company RTX.

 

 

 

Ojú-ìwé yìí nlo kuki

A nlo kuki fun itupalẹ lati mu ilọsiwaju wa. Ka ìlànà àṣírí wa fun alaye siwaju sii.
Kọ