Auditors flag delays and cost overruns in Clark air traffic control tower project

State auditors have flagged the P290.3-million New Clark Air Traffic Control Tower project for repeated extensions and cost increases, leaving it unfinished without a target completion date.

The P290.3-million New Clark Air Traffic Control Tower project was awarded in January 2021 with an expected completion within one year. A 2024 audit report by the Commission on Audit (COA) on the Clark International Airport Corporation (CIAC) revealed it has been extended six times, adding 930 days to the original 365-day contract, yet only 91% complete as of 2024. Costs have risen 22% to P354.41 million.

Auditors attributed delays to weak procurement planning, poor project monitoring, and possible shortcomings in the contractor's capacity. Groundbreaking occurred without required building, electronic, electrical, mechanical, plumbing, and sanitary permits from the Clark Development Corporation (CDC), the regulator for the Clark Freeport Zone. Under the National Building Code, such permits are mandatory, with penalties up to P20,000 fines or two years imprisonment.

"It was only on April 29, 2024 that CIAC was able to secure the necessary permits from the CDC. The absence of necessary permits during the construction period raises serious concerns regarding regulatory compliance, project authorization, and risk management," the report stated.

The contractor requested a suspension of the height clearance limit on March 17, 2022—two months after the original January 2022 completion date—after the Civil Aviation Authority of the Philippines (CAAP) denied permits for exceeding the 192-meter limit, with the tower's proposed top elevation at 228.81 meters (36.81-meter excess). An aeronautical study costing P3.9 million was submitted to CAAP on October 11, 2023, but the permit remains unissued as of December 31, 2024.

Additionally, installed elevators did not match the billed brand; a Global Fuji (Chinese) was found instead of the specified Schneider (German), approved by CIAC's then president during a March 20, 2025 inspection.

"Securing permits is a fundamental requirement in the construction industry, and failure to do so casts doubt on the contractor’s capability to manage regulatory requirements effectively," the report added, highlighting deficiencies in due diligence.

Verwandte Artikel

Das Cape Winelands Airport-Projekt im Wert von 8 Milliarden R nahe Durbanville soll den Bau Ende 2026 beginnen, abhängig von der Klärung der Einsprüche von Landbesitzern an den Umweltminister des Western Cape. Das Vorhaben zielt darauf ab, regionale Reisen zu verbessern, Treibstoffkosten für Fluggesellschaften zu senken und Tausende von Arbeitsplätzen zu schaffen. Umweltgenehmigungen wurden im Oktober 2025 erteilt, aber Bedenken hinsichtlich Lärm und Landnutzung bestehen weiterhin.

Von KI berichtet

As the country grapples with the fallout from a massive infrastructure scam, a flood control project continues on reclaimed land in Laguna de Bay. The contractor is Topnotch Catalyst Builders Inc., implicated in Bulacan's ghost flood control projects. Investigation shows Phase 1 in Taguig City is 70.08% complete.

Andrés Conesa, CEO von Aeroméxico, wiederholte, dass der Bau eines dritten Terminals am Flughafen AICM in Mexiko-Stadt essenziell ist, um die Kapazität im Tal von Mexiko auf 100 Millionen Passagiere pro Jahr auszuweiten, indem AICM, AIFA und Toluca kombiniert werden. Conesa würdigte laufende Arbeiten am AICM im Vorfeld der FIFA-Weltmeisterschaft 2026 und vermied Kommentare zu Vorschlägen für einen einzigen Flughafen in Texcoco. Experten warnen, dass das aktuelle System ineffizient ist, mit gesättigten Lufträumen und steigenden Betriebskosten.

Von KI berichtet

A Hong Kong lawmaker has warned that the government's proposed moves to increase professional scrutiny of building maintenance projects could incur extra costs and delays. Election Committee lawmaker Andrew Lam Siu-lo called for deeper discussions on implementation details by the government and legislature. The measures respond to the deadly Tai Po inferno in late November.

 

 

 

Diese Website verwendet Cookies

Wir verwenden Cookies für Analysen, um unsere Website zu verbessern. Lesen Sie unsere Datenschutzrichtlinie für weitere Informationen.
Ablehnen