Auditors flag delays and cost overruns in Clark air traffic control tower project

State auditors have flagged the P290.3-million New Clark Air Traffic Control Tower project for repeated extensions and cost increases, leaving it unfinished without a target completion date.

The P290.3-million New Clark Air Traffic Control Tower project was awarded in January 2021 with an expected completion within one year. A 2024 audit report by the Commission on Audit (COA) on the Clark International Airport Corporation (CIAC) revealed it has been extended six times, adding 930 days to the original 365-day contract, yet only 91% complete as of 2024. Costs have risen 22% to P354.41 million.

Auditors attributed delays to weak procurement planning, poor project monitoring, and possible shortcomings in the contractor's capacity. Groundbreaking occurred without required building, electronic, electrical, mechanical, plumbing, and sanitary permits from the Clark Development Corporation (CDC), the regulator for the Clark Freeport Zone. Under the National Building Code, such permits are mandatory, with penalties up to P20,000 fines or two years imprisonment.

"It was only on April 29, 2024 that CIAC was able to secure the necessary permits from the CDC. The absence of necessary permits during the construction period raises serious concerns regarding regulatory compliance, project authorization, and risk management," the report stated.

The contractor requested a suspension of the height clearance limit on March 17, 2022—two months after the original January 2022 completion date—after the Civil Aviation Authority of the Philippines (CAAP) denied permits for exceeding the 192-meter limit, with the tower's proposed top elevation at 228.81 meters (36.81-meter excess). An aeronautical study costing P3.9 million was submitted to CAAP on October 11, 2023, but the permit remains unissued as of December 31, 2024.

Additionally, installed elevators did not match the billed brand; a Global Fuji (Chinese) was found instead of the specified Schneider (German), approved by CIAC's then president during a March 20, 2025 inspection.

"Securing permits is a fundamental requirement in the construction industry, and failure to do so casts doubt on the contractor’s capability to manage regulatory requirements effectively," the report added, highlighting deficiencies in due diligence.

Artigos relacionados

Realistic illustration of a press conference announcing charges against senators in a flood control kickback scandal, with documents and public frustration depicted.
Imagem gerada por IA

ICI recommends charges against senators in flood control scandal

Reportado por IA Imagem gerada por IA

The Independent Commission for Infrastructure has recommended criminal and administrative complaints against Senators Joel Villanueva and Jinggoy Estrada, former Representative Zaldy Co, and three others over alleged kickbacks in flood control projects. Related probes include a forged affidavit by a Senate witness linked to Co and efforts to forfeit implicated assets. Lawmakers are pushing for a stronger anti-corruption body amid public frustration with the inquiry's pace.

A Architectural Association of Kenya detalhou múltiplas falhas regulatórias precedendo o colapso de um edifício de 14 andares em South C em 2 de janeiro de 2026. Em seu comunicado, apontaram ordens de parada ignoradas e aprovações inadequadas. O grupo urge investigações e supervisão mais rigorosa na construção.

Reportado por IA

O debate sobre o Novo Aeroporto Internacional do México (NAIM) em Texcoco reacendeu após um engenheiro hidráulico afirmar que o projeto incluía medidas de prevenção de inundações. Especialistas em aviação pediram a retomada da construção em um fórum recente. Isso desafia os argumentos do cancelamento de 2018.

Ombudsman Jesus Crispin Remulla said the Independent Commission for Infrastructure (ICI) might last only a month or two. However, ICI Chair Andres Reyes Jr. countered that the commission is set for two years of operation. The controversy stems from recent statements about the commission's powers and future.

Reportado por IA

The Bureau of Internal Revenue (BIR) has filed tax evasion complaints against Mark Arevalo, owner of Wawao Builders, over a P48.39 million tax deficiency from a non-existent flood control project in Malolos, Bulacan. The P77.20 million project received P72.37 million in payments, yet no structure was built despite claims of 100% completion. This marks the 13th such complaint by the BIR, with total potential tax liabilities reaching P8.92 billion.

O tráfego aéreo doméstico da Nigéria enfrentará perturbações em 2026. A Air Traffic and Services Senior Staff Association of Nigeria (ATSSSAN) instou o governo federal a rever as taxas de navegação impostas pela Nigerian Airspace Management Agency (NAMA). Este apelo destaca as preocupações contínuas no setor de aviação.

Reportado por IA

A empresa espanhola Indra assegurou um contrato de quase 300 milhões de euros com a Federal Aviation Administration dos EUA para atualizar os sistemas de controlo de tráfego aéreo. O acordo visa substituir radares obsoletos e melhorar a segurança dos voos. Complementa um projeto semelhante atribuído à empresa norte-americana RTX.

quarta-feira, 04 de fevereiro de 2026, 10:44h

Aeroméxico insiste no Terminal 3 no AICM para o país

quinta-feira, 22 de janeiro de 2026, 09:32h

Can Hong Kong find quick fixes for corruption in building maintenance?

sábado, 17 de janeiro de 2026, 13:49h

Ruto anuncia início da construção de novo aeroporto em abril ou maio

quinta-feira, 15 de janeiro de 2026, 02:18h

Hong Kong lawmaker says tougher building checks may add costs, slow projects

domingo, 11 de janeiro de 2026, 16:32h

NCA suspends Karen site after fatal building collapse

quarta-feira, 07 de janeiro de 2026, 08:12h

Hong Kong firms to resume projects as new scaffolding nets arrive soon

segunda-feira, 05 de janeiro de 2026, 04:34h

Colapso em South C: Governo confirma pisos extras ilegais pelos promotores

domingo, 28 de dezembro de 2025, 21:03h

COA recommends PAGASA speed up Doppler radar repairs

quinta-feira, 18 de dezembro de 2025, 11:09h

Cathay Pacific investigates wrong taxiway use at Manila airport

quarta-feira, 03 de dezembro de 2025, 22:54h

Hong Kong firms remove scaffolding nets to meet deadline

 

 

 

Este site usa cookies

Usamos cookies para análise para melhorar nosso site. Leia nossa política de privacidade para mais informações.
Recusar