Auditors flag delays and cost overruns in Clark air traffic control tower project

State auditors have flagged the P290.3-million New Clark Air Traffic Control Tower project for repeated extensions and cost increases, leaving it unfinished without a target completion date.

The P290.3-million New Clark Air Traffic Control Tower project was awarded in January 2021 with an expected completion within one year. A 2024 audit report by the Commission on Audit (COA) on the Clark International Airport Corporation (CIAC) revealed it has been extended six times, adding 930 days to the original 365-day contract, yet only 91% complete as of 2024. Costs have risen 22% to P354.41 million.

Auditors attributed delays to weak procurement planning, poor project monitoring, and possible shortcomings in the contractor's capacity. Groundbreaking occurred without required building, electronic, electrical, mechanical, plumbing, and sanitary permits from the Clark Development Corporation (CDC), the regulator for the Clark Freeport Zone. Under the National Building Code, such permits are mandatory, with penalties up to P20,000 fines or two years imprisonment.

"It was only on April 29, 2024 that CIAC was able to secure the necessary permits from the CDC. The absence of necessary permits during the construction period raises serious concerns regarding regulatory compliance, project authorization, and risk management," the report stated.

The contractor requested a suspension of the height clearance limit on March 17, 2022—two months after the original January 2022 completion date—after the Civil Aviation Authority of the Philippines (CAAP) denied permits for exceeding the 192-meter limit, with the tower's proposed top elevation at 228.81 meters (36.81-meter excess). An aeronautical study costing P3.9 million was submitted to CAAP on October 11, 2023, but the permit remains unissued as of December 31, 2024.

Additionally, installed elevators did not match the billed brand; a Global Fuji (Chinese) was found instead of the specified Schneider (German), approved by CIAC's then president during a March 20, 2025 inspection.

"Securing permits is a fundamental requirement in the construction industry, and failure to do so casts doubt on the contractor’s capability to manage regulatory requirements effectively," the report added, highlighting deficiencies in due diligence.

Articoli correlati

The R8 billion Cape Winelands Airport project near Durbanville is set to begin construction in late 2026, pending resolution of landowner appeals to the Western Cape environmental minister. The development aims to enhance regional travel, reduce airline fuel costs, and create thousands of jobs. Environmental approvals were granted in October 2025, but concerns over noise and land use persist.

Riportato dall'IA

As the country grapples with the fallout from a massive infrastructure scam, a flood control project continues on reclaimed land in Laguna de Bay. The contractor is Topnotch Catalyst Builders Inc., implicated in Bulacan's ghost flood control projects. Investigation shows Phase 1 in Taguig City is 70.08% complete.

Andrés Conesa, CEO di Aeroméxico, ha ribadito che la costruzione di un terzo terminal all’Aeroporto Internazionale della Città del Messico (AICM) è essenziale per espandere la capacità nella Valle del Messico a 100 milioni di passeggeri annui, combinando AICM, AIFA e Toluca. Conesa ha riconosciuto i lavori in corso all’AICM in vista della Coppa del Mondo FIFA 2026 ed ha evitato di commentare le proposte per un unico aeroporto a Texcoco. Gli esperti avvertono che il sistema attuale è inefficiente, con cieli saturi e costi operativi in aumento.

Riportato dall'IA

A Hong Kong lawmaker has warned that the government's proposed moves to increase professional scrutiny of building maintenance projects could incur extra costs and delays. Election Committee lawmaker Andrew Lam Siu-lo called for deeper discussions on implementation details by the government and legislature. The measures respond to the deadly Tai Po inferno in late November.

 

 

 

Questo sito web utilizza i cookie

Utilizziamo i cookie per l'analisi per migliorare il nostro sito. Leggi la nostra politica sulla privacy per ulteriori informazioni.
Rifiuta