Illustration of layoffs at Hedemora logistics firm amid Garpenberg mine production halt.
Illustration of layoffs at Hedemora logistics firm amid Garpenberg mine production halt.
Imagen generada por IA

La empresa de logística Långdahls de Hedemora anuncia despidos tras el derrumbe y los terremotos en la mina de Garpenberg

Imagen generada por IA

La empresa Långdahls logistik, con sede en Hedemora, ha emitido avisos de despido a varios empleados debido a la escasez de trabajo tras la paralización de la mina de Garpenberg de Boliden, causada por un derrumbe y varios terremotos, incluido uno de gran magnitud el 14 de marzo que dejó cuatro personas hospitalizadas. Boliden no ha anunciado despidos. SVT Nyheter Dalarna fue el primer medio en informar sobre el suceso.

Långdahls logistik AB, que se encarga del transporte de mineral desde la mina de Garpenberg, ha emitido avisos de despido debido al cese de actividad en la mina provocado por un derrumbe y los posteriores terremotos.

El director general, Elving Långdahl, declaró: “Långdahls ha decidido hoy emitir avisos de despido a varios empleados debido a la escasez de trabajo. Es un paso difícil pero necesario para adaptar nuestras operaciones a la situación económica actual”.

El potente terremoto del 14 de marzo provocó el derrumbe, dejando a cuatro personas hospitalizadas, y fue seguido por más sismos. Como consecuencia, Boliden no podrá explotar uno de los tres yacimientos de la mina durante el resto del año.

El jefe de comunicación de Boliden, Klas Nilsson, señaló: “No hemos anunciado ningún despido y seguimos trabajando en la situación a la que nos enfrentamos, manteniendo una firme confianza a largo plazo en la mina de Garpenberg”.

SVT Nyheter Dalarna fue el primero en informar sobre los despidos, según Dala-Demokraten. La paralización tiene consecuencias directas para las empresas de transporte locales.

Artículos relacionados

Damaged underground tunnel in Garpenberg mine, closed until 2026 due to earthquakes, with cracks, debris, and warning barriers.
Imagen generada por IA

Parts of Garpenberg mine closed through 2026 after quakes

Reportado por IA Imagen generada por IA

Following a series of seismic events at the Garpenberg mine in Hedemora, Boliden announced that large parts of the mine will remain closed throughout 2026. The company expects to lose 70 percent of planned production and incur a 400 million kronor loss in the first quarter.

A Swiss subcontractor to Boliden is laying off about 30 employees at Garpenbergs mine in Hedemora, following the March 14 collapse that injured three workers and halted production. The mine had been one of Boliden's most profitable operations.

Reportado por IA

Production at Garpenberg mine in Hedemora has been halted after a rockfall and hundreds of subsequent mine tremors over the weekend. Several people were injured, and all employees were evacuated on Saturday. Around 500 workers are now operating above ground.

Boliden plans a new hoisting shaft at its Garpenberg mine to boost production to 4.5 million tons annually, following a weekend collapse that injured workers and ongoing high seismic activity halting underground operations. The investment builds on earlier announcements amid disruptions.

Reportado por IA

Boliden has announced a 700 million kronor write-down of assets at the Garpenberg mine, damaged by seismic activity and a collapse in March that led to parts of the mine closing through 2026. The write-down covers infrastructure and equipment affected by the events.

SSAB has stopped all work on its new steel mill construction in Luleå after three people sought medical care due to suspected toxic gas exposure. Earlier tests revealed elevated levels in machine cabins, with new cases reported on Good Friday. Region Norrbotten confirms two of the affected remain at the emergency department.

Reportado por IA

Several employees at SSAB's site in Luleå have sought medical help after earthworks near the new steel mill. They reported nausea and headaches. Work has been halted in the affected construction area pending soil test results.

 

 

 