World-unique train replaces rails between Borlänge and Ludvika

A kilometer-long track replacement train is currently upgrading the railway between Ludvika and Ulvshyttan. The work will last five weeks and costs around 400 million kronor.

Around 200 people are involved in the effort where ballast, sleepers and rails are replaced at the same time. The Swedish Transport Administration is using the world-unique train that can replace track at a rate of 200 meters per hour.

Train passengers are directed to replacement services during the period. The section will reopen partially from 1 June and is expected to be fully operational by mid-June.

The project is part of several major railway investments in Dalarna. Other works are ongoing between Grängesberg and Ställdalen as well as between Avesta-Krylbo and Uppsala.

Relaterede artikler

Centerpartiet politician announces partial support for Uppsala tram project at construction site.
Billede genereret af AI

Centerpartiet partially reverses stance on Uppsala tram project

Rapporteret af AI Billede genereret af AI

Centerpartiet has partially reversed its opposition to Uppsala's tram project, now favoring construction of half the route rather than canceling it entirely. The decision stems from estimated cancellation costs of 3.8 to 4.2 billion kronor. Oppositionsråd Ehsan Nasari (C) stated that scrapping the whole project is no longer economically defensible.

Den 31. marts meddelte Trafikverket, at de har tildelt den spanske virksomhed Talgo en kontrakt på 10 lokomotiver og 91 vogne til nye nattog. Togene skal erstatte de nuværende nattog mellem Stockholm og Narvik fra 2030. Kontrakten har en værdi på 5,5 milliarder svenske kroner.

Rapporteret af AI

The Swedish government has approved the expansion to four railway tracks between Uppsala and Stockholm. The decision removes the last remaining doubts about the project, aligning with the 2017 four-track agreement. The national plan secures funding for completion by 2034, including new stations.

The upgrade of Vasaloppsvägen between Oxberg and Fiskarheden will cost at least 150 million kronor more than planned. Extra costs have risen further over the winter. This now threatens other road projects in Dalarna.

Rapporteret af AI

Tirsdag samledes tilskuere ved Viktoriaslussen i Stockholm for at overvære den første sektion af en ny cykel- og gangbro blive bugseret ind i Söderström. Den 220 meter lange bro, som er bygget i Polen, er blevet opdelt i seks sektioner af hensyn til transportbegrænsninger. Installationsarbejdet går nu i gang og forventes at vare seks uger.

Det regerende flertal i udvalget for offentlig transport har inkluderet genstarten af buslinje 404 i deres kommende budget. Linjen mellem Karlskoga og Hällefors blev nedlagt den 14. december sidste år.

Rapporteret af AI

Med seks ugers forsinkelse er togstrækningen mellem Hamburg og Berlin genåbnet. Det første fjerntog afgik fra Hamburg Hauptbahnhof søndag morgen.

 

 

 